New LNG Export Capacity

Enercast’s own survey of 35 LNG export projects that liquefy U.S. natural gas: new terminals, new trains at existing ones, uprates and floating LNG, on the Gulf Coast, the East Coast, Alaska and in Mexico, from proposed to newly in service.

Compiled by Enercast from FERC filings · DOE export authorizations · Sponsors’ public material · EIA liquefaction data

Also tracked 11 proposed, 24.05 Bcf/d stated · announced, in pre-filing or applied

The website and free subscribers get updates weekly. Pro subscribers get them daily.

Under construction
17.86Bcf/d stated
8 projects with a final investment decision, 103.9 MTPA stated for 7
Commissioning
4.45Bcf/d stated
2 projects producing first LNG, not yet fully in service, 18.1 MTPA stated for 1
In service, last 12 months
1.94Bcf/d stated
2 projects completed, 14.7 MTPA stated for 2
Approved, no FID yet
13.83Bcf/d stated
11 projects authorized, not yet building, 44.0 MTPA stated for 3

Every status, date and capacity here comes from a named source: FERC’s list of LNG export terminals and its dockets, the Department of Energy’s export authorizations, MARAD for offshore terminals, EIA’s liquefaction capacity file, the sponsor’s own pages, or trade press.

Capacity is the Bcf/d the source states, with the basis beside it (FERC’s authorized figure, EIA’s nominal figure, the sponsor’s), and in MTPA where the source gives it; the two units are never added together. Timing is in the source’s own words. Enercast checks the sources every night; a change is published only if it passes automatic checks against its source, and the riskier kinds are held for a manual check first. 1 project is marked No regulator filing yet. How this page works.

New LNG export capacity by in-service year

Enercastenercast.com

Bcf/d of stated liquefaction capacity, stacked by project status, in the year (or quarter) each project’s sponsor or regulator says it will start, from 2026 on. Click a status to hide or show it. Projects with no stated Bcf/d are not in the chart. In the quarterly view, a project whose source gives only a year sits in that year’s paler yr column. Capacity is stated on different bases (FERC’s authorized figure, EIA’s nominal figure, the sponsor’s), so the totals are indicative. This is what sponsors and regulators have said, added up, not a forecast: trains start one at a time over a year or more, and approved projects may never be built.

View the yearly numbers as a table
Status2026202720282029203020312034No date
In service1.94———————
Commissioning—4.45——————
Under construction—9.980.43.813.67———
Approved—2.6——0.62——10.61
Applied—6.07—————7.16
Pre-filing————3.45—3.722.65
Announced———————1
On hold—————2.27——
All shown1.9423.10.43.817.742.273.7221.42

Where the projects are

HoustonBeaumontLake CharlesNew OrleansCorpus ChristiBrownsville
Enercastenercast.com

Capacity offline (updated every run): one marker per event in effect or scheduled, sized by Bcf/d; green bullish, red bearish, grey basis-only; hollow unquantified, dashed purple scheduled, teal ring lifted in the last 7 days.

One square per project at the approximate terminal site (projects at the same terminal are offset), colored by status as in the chart and sized by stated capacity in Bcf/d. Hollow: capacity not stated. Click a status to hide or show it (On hold starts hidden). Drag to move, scroll to zoom. Outside this view: Jacksonville LNG (FL); Energia Costa Azul Phase 1 (Baja California); Mexico Pacific Saguaro LNG (Sonora); Epcilon LNG (Sonora); Vista Pacifico LNG (Sinaloa); Alaska LNG (AK, off the map). Open on the full map with pipelines, storage and capacity offline →

Changed in the last 7 days

1 change recorded.

ProjectBcf/dChangedPreviousUpdated
Sabine Pass Stage 5 Expansion2.6Milestone—FERC authorization, Nov 19, 2026

Bcf/d is each project’s stated capacity. “Previous” and “Updated” are the values before and after the change Enercast recorded; the source is shown beside the new value.

Projects

35 projects

ProjectBcf/d statedMTPA statedStatusStated timingVerified
Golden Pass LNG (Trains 1-3)QatarEnergy 70% / ExxonMobil 30% · TX · US Gulf Coast2.57FERC list18.1CommissioningT2 1H 2027Nov 27, 2026
Plaquemines LNG Phase 2 (Blocks 10-18)Venture Global · LA · US Gulf Coast1.88FERC list—CommissioningPhase 2 commercial deliveries mid-2027Nov 27, 2026
Rio Grande LNG (Trains 1-5)NextDecade · TX · US Gulf Coast4.16FERC list30Under constructionT1-3 2027; T5 early 2031Nov 27, 2026
CP2 LNG Phases 1-2Venture Global · LA · US Gulf Coast3.96FERC list29Under constructionfirst LNG July 2027Nov 27, 2026
Port Arthur LNG Phase 1 (Trains 1-2)Sempra Infrastructure · TX · US Gulf Coast1.86derived (FERC list split)13Under constructionT1 2027; T2 2028Nov 27, 2026
Corpus Christi Midscale Trains 8-9Cheniere · TX · US Gulf Coast0.4EIA nominal5Under construction2028Nov 27, 2026
Louisiana LNG (formerly Driftwood)Woodside · LA · US Gulf Coast3.81FERC list—Under construction2029 (est., DOE)Nov 27, 2026
Port Arthur LNG Phase 2 (Trains 3-4)not yet re-checkedSempra Infrastructure · TX · US Gulf Coast1.86derived (FERC list split)13Under constructionT3 2030; T4 2031—
Commonwealth LNG Phase 1Kimmeridge / Mubadala / CPPIB · LA · US Gulf Coast1.21FERC list9.5Under constructionfirst LNG 2030Nov 25, 2026
Delfin FLNG 1Delfin Midstream · LA (federal waters) · US Gulf Coast0.6DOE4.4Under construction2030Nov 27, 2026
Sabine Pass Stage 5 ExpansionCheniere · LA · US Gulf Coast2.6FERC list20ApprovedFID early 2027Nov 27, 2026
Texas LNGGlenfarne · TX · US Gulf Coast0.62FERC list4Approvedops ~2030Nov 27, 2026
Alaska LNGGlenfarne / Alaska Gasline · AK · Alaska2.76FERC list20ApprovedNot statedNov 27, 2026
Mexico Pacific Saguaro LNGnot yet re-checkedMexico Pacific · Sonora · Mexico (US-fed)1.7DOE—ApprovedNot stated—
Gulf LNG LiquefactionKinder Morgan · MS · US Gulf Coast1.5FERC list—ApprovedNot statedNov 27, 2026
Magnolia LNGGlenfarne · LA · US Gulf Coast1.22FERC list—ApprovedNot statedNov 27, 2026
Epcilon LNGnot yet re-checkedEpcilon · Sonora · Mexico (US-fed)1.08DOE—ApprovedNot stated—
Cameron LNG Train 4Sempra · LA · US Gulf Coast0.93FERC list—ApprovedNot statedNov 27, 2026
Freeport LNG Train 4Freeport LNG · TX · US Gulf Coast0.74FERC list—ApprovedNot statedNov 27, 2026
Vista Pacifico LNGnot yet re-checkedVista Pacifico · Sinaloa · Mexico (US-fed)0.55DOE—ApprovedNot stated—
Jacksonville LNGEagle LNG · FL · US East Coast0.13FERC list—ApprovedNot statedNov 27, 2026
CP2 LNG ExpansionVenture Global · LA · US Gulf Coast1.62FERC list10AppliedFID early 2027Nov 27, 2026
Plaquemines LNG ExpansionVenture Global · LA · US Gulf Coast4.45FERC list—AppliedFID H1 2027Nov 27, 2026
Corpus Christi Liquefaction Stage 4Cheniere · TX · US Gulf Coast3.32FERC list24AppliedNot statedNov 27, 2026
Plaquemines LNG UprateVenture Global · LA · US Gulf Coast1.29FERC list—AppliedNot statedNov 27, 2026
CP2 LNG UprateVenture Global · LA · US Gulf Coast1.17FERC list—AppliedNot statedNov 27, 2026
Rio Grande LNG ExpansionNextDecade · TX · US Gulf Coast0.83FERC list—AppliedNot statedNov 27, 2026
Gulfstream LNGGulfstream LNG Development · LA · US Gulf Coast0.55FERC list—AppliedNot statedNov 27, 2026
Argent LNGArgent LNG · LA · US Gulf Coast3.45FERC list25Pre-filingearly 2030Nov 27, 2026
Port Arthur LNG North (Trains 5-8)Sempra Infrastructure · TX · US Gulf Coast3.72FERC list27Pre-filingT5 2H 2034; T8 1H 2036Nov 27, 2026
Coastal Bend LNGCoastal Bend LNG · TX · US Gulf Coast2.65FERC list—Pre-filingNot statedNov 27, 2026
Commonwealth LNG ExpansionNo regulator filing yetnot yet re-checkedCaturus · LA · US Gulf Coast1trade press7.75Announcedearly 2030s—
Energia Costa Azul Phase 1not yet re-checkedSempra Infrastructure · Baja California · Mexico (US-fed)0.44DOE3.25In serviceIn service—
Corpus Christi Liquefaction Stage 3 (Midscale Trains 1-7)not yet re-checkedCheniere · TX · US Gulf Coast1.5trade press11.45In serviceIn service Aug 28, 2026—
Lake Charles LNGEnergy Transfer · LA · US Gulf Coast2.27FERC list16.5On holdin-service deadline 2031 (FERC extension)Nov 27, 2026
About this dataOne row per LNG export project of 0.1 Bcf/d or more that liquefies U.S. gas: Lower 48, Alaska, offshore, and Mexican terminals fed by U.S. pipeline gas, compiled from FERC, DOE, MARAD, EIA, sponsors’ public material and trade press; capacity and timing are as stated by the source, not measured.