Every status, date and capacity here comes from a named source: FERC’s list of LNG export terminals and its dockets, the Department of Energy’s export authorizations, MARAD for offshore terminals, EIA’s liquefaction capacity file, the sponsor’s own pages, or trade press.
Capacity is the Bcf/d the source states, with the basis beside it (FERC’s authorized figure, EIA’s nominal figure, the sponsor’s), and in MTPA where the source gives it; the two units are never added together. Timing is in the source’s own words. Enercast checks the sources every night; a change is published only if it passes automatic checks against its source, and the riskier kinds are held for a manual check first. 1 project is marked No regulator filing yet. How this page works.
New LNG export capacity by in-service year
Bcf/d of stated liquefaction capacity, stacked by project status, in the year (or quarter) each project’s sponsor or regulator says it will start, from 2026 on. Click a status to hide or show it. Projects with no stated Bcf/d are not in the chart. In the quarterly view, a project whose source gives only a year sits in that year’s paler yr column. Capacity is stated on different bases (FERC’s authorized figure, EIA’s nominal figure, the sponsor’s), so the totals are indicative. This is what sponsors and regulators have said, added up, not a forecast: trains start one at a time over a year or more, and approved projects may never be built.
View the yearly numbers as a table
| Status | 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | 2034 | No date |
|---|---|---|---|---|---|---|---|---|
| In service | 1.94 | — | — | — | — | — | — | — |
| Commissioning | — | 4.45 | — | — | — | — | — | — |
| Under construction | — | 9.98 | 0.4 | 3.81 | 3.67 | — | — | — |
| Approved | — | 2.6 | — | — | 0.62 | — | — | 10.61 |
| Applied | — | 6.07 | — | — | — | — | — | 7.16 |
| Pre-filing | — | — | — | — | 3.45 | — | 3.72 | 2.65 |
| Announced | — | — | — | — | — | — | — | 1 |
| On hold | — | — | — | — | — | 2.27 | — | — |
| All shown | 1.94 | 23.1 | 0.4 | 3.81 | 7.74 | 2.27 | 3.72 | 21.42 |
Where the projects are
Capacity offline (updated every run): one marker per event in effect or scheduled, sized by Bcf/d; green bullish, red bearish, grey basis-only; hollow unquantified, dashed purple scheduled, teal ring lifted in the last 7 days.
One square per project at the approximate terminal site (projects at the same terminal are offset), colored by status as in the chart and sized by stated capacity in Bcf/d. Hollow: capacity not stated. Click a status to hide or show it (On hold starts hidden). Drag to move, scroll to zoom. Outside this view: Jacksonville LNG (FL); Energia Costa Azul Phase 1 (Baja California); Mexico Pacific Saguaro LNG (Sonora); Epcilon LNG (Sonora); Vista Pacifico LNG (Sinaloa); Alaska LNG (AK, off the map). Open on the full map with pipelines, storage and capacity offline →
Changed in the last 7 days
1 change recorded.
| Project | Bcf/d | Changed | Previous | Updated |
|---|---|---|---|---|
| Sabine Pass Stage 5 Expansion | 2.6 | Milestone | — | FERC authorization, Nov 19, 2026 |
Bcf/d is each project’s stated capacity. “Previous” and “Updated” are the values before and after the change Enercast recorded; the source is shown beside the new value.
Projects
35 projects
| Project | Bcf/d stated | MTPA stated | Status | Stated timing | Verified |
|---|---|---|---|---|---|
| Golden Pass LNG (Trains 1-3)QatarEnergy 70% / ExxonMobil 30% · TX · US Gulf Coast | 2.57FERC list | 18.1 | Commissioning | T2 1H 2027 | Nov 27, 2026 |
| Plaquemines LNG Phase 2 (Blocks 10-18)Venture Global · LA · US Gulf Coast | 1.88FERC list | — | Commissioning | Phase 2 commercial deliveries mid-2027 | Nov 27, 2026 |
| Rio Grande LNG (Trains 1-5)NextDecade · TX · US Gulf Coast | 4.16FERC list | 30 | Under construction | T1-3 2027; T5 early 2031 | Nov 27, 2026 |
| CP2 LNG Phases 1-2Venture Global · LA · US Gulf Coast | 3.96FERC list | 29 | Under construction | first LNG July 2027 | Nov 27, 2026 |
| Port Arthur LNG Phase 1 (Trains 1-2)Sempra Infrastructure · TX · US Gulf Coast | 1.86derived (FERC list split) | 13 | Under construction | T1 2027; T2 2028 | Nov 27, 2026 |
| Corpus Christi Midscale Trains 8-9Cheniere · TX · US Gulf Coast | 0.4EIA nominal | 5 | Under construction | 2028 | Nov 27, 2026 |
| Louisiana LNG (formerly Driftwood)Woodside · LA · US Gulf Coast | 3.81FERC list | — | Under construction | 2029 (est., DOE) | Nov 27, 2026 |
| Port Arthur LNG Phase 2 (Trains 3-4)not yet re-checkedSempra Infrastructure · TX · US Gulf Coast | 1.86derived (FERC list split) | 13 | Under construction | T3 2030; T4 2031 | — |
| Commonwealth LNG Phase 1Kimmeridge / Mubadala / CPPIB · LA · US Gulf Coast | 1.21FERC list | 9.5 | Under construction | first LNG 2030 | Nov 25, 2026 |
| Delfin FLNG 1Delfin Midstream · LA (federal waters) · US Gulf Coast | 0.6DOE | 4.4 | Under construction | 2030 | Nov 27, 2026 |
| Sabine Pass Stage 5 ExpansionCheniere · LA · US Gulf Coast | 2.6FERC list | 20 | Approved | FID early 2027 | Nov 27, 2026 |
| Texas LNGGlenfarne · TX · US Gulf Coast | 0.62FERC list | 4 | Approved | ops ~2030 | Nov 27, 2026 |
| Alaska LNGGlenfarne / Alaska Gasline · AK · Alaska | 2.76FERC list | 20 | Approved | Not stated | Nov 27, 2026 |
| Mexico Pacific Saguaro LNGnot yet re-checkedMexico Pacific · Sonora · Mexico (US-fed) | 1.7DOE | — | Approved | Not stated | — |
| Gulf LNG LiquefactionKinder Morgan · MS · US Gulf Coast | 1.5FERC list | — | Approved | Not stated | Nov 27, 2026 |
| Magnolia LNGGlenfarne · LA · US Gulf Coast | 1.22FERC list | — | Approved | Not stated | Nov 27, 2026 |
| Epcilon LNGnot yet re-checkedEpcilon · Sonora · Mexico (US-fed) | 1.08DOE | — | Approved | Not stated | — |
| Cameron LNG Train 4Sempra · LA · US Gulf Coast | 0.93FERC list | — | Approved | Not stated | Nov 27, 2026 |
| Freeport LNG Train 4Freeport LNG · TX · US Gulf Coast | 0.74FERC list | — | Approved | Not stated | Nov 27, 2026 |
| Vista Pacifico LNGnot yet re-checkedVista Pacifico · Sinaloa · Mexico (US-fed) | 0.55DOE | — | Approved | Not stated | — |
| Jacksonville LNGEagle LNG · FL · US East Coast | 0.13FERC list | — | Approved | Not stated | Nov 27, 2026 |
| CP2 LNG ExpansionVenture Global · LA · US Gulf Coast | 1.62FERC list | 10 | Applied | FID early 2027 | Nov 27, 2026 |
| Plaquemines LNG ExpansionVenture Global · LA · US Gulf Coast | 4.45FERC list | — | Applied | FID H1 2027 | Nov 27, 2026 |
| Corpus Christi Liquefaction Stage 4Cheniere · TX · US Gulf Coast | 3.32FERC list | 24 | Applied | Not stated | Nov 27, 2026 |
| Plaquemines LNG UprateVenture Global · LA · US Gulf Coast | 1.29FERC list | — | Applied | Not stated | Nov 27, 2026 |
| CP2 LNG UprateVenture Global · LA · US Gulf Coast | 1.17FERC list | — | Applied | Not stated | Nov 27, 2026 |
| Rio Grande LNG ExpansionNextDecade · TX · US Gulf Coast | 0.83FERC list | — | Applied | Not stated | Nov 27, 2026 |
| Gulfstream LNGGulfstream LNG Development · LA · US Gulf Coast | 0.55FERC list | — | Applied | Not stated | Nov 27, 2026 |
| Argent LNGArgent LNG · LA · US Gulf Coast | 3.45FERC list | 25 | Pre-filing | early 2030 | Nov 27, 2026 |
| Port Arthur LNG North (Trains 5-8)Sempra Infrastructure · TX · US Gulf Coast | 3.72FERC list | 27 | Pre-filing | T5 2H 2034; T8 1H 2036 | Nov 27, 2026 |
| Coastal Bend LNGCoastal Bend LNG · TX · US Gulf Coast | 2.65FERC list | — | Pre-filing | Not stated | Nov 27, 2026 |
| Commonwealth LNG ExpansionNo regulator filing yetnot yet re-checkedCaturus · LA · US Gulf Coast | 1trade press | 7.75 | Announced | early 2030s | — |
| Energia Costa Azul Phase 1not yet re-checkedSempra Infrastructure · Baja California · Mexico (US-fed) | 0.44DOE | 3.25 | In service | In service | — |
| Corpus Christi Liquefaction Stage 3 (Midscale Trains 1-7)not yet re-checkedCheniere · TX · US Gulf Coast | 1.5trade press | 11.45 | In service | In service Aug 28, 2026 | — |
| Lake Charles LNGEnergy Transfer · LA · US Gulf Coast | 2.27FERC list | 16.5 | On hold | in-service deadline 2031 (FERC extension) | Nov 27, 2026 |