Golden Pass LNG (Trains 1-3) is a new LNG export terminal by QatarEnergy 70% / ExxonMobil 30% in TX. It is commissioning: producing first LNG, but not yet fully in commercial operation. Stated liquefaction capacity is 2.57 Bcf/d (FERC list figure), or 18.1 MTPA. Trains: 3. Timing is stated as T2 1H 2027. FERC dockets CP14-517, CP20-459. Sources: FERC, the Department of Energy, the sponsor's public material, trade press and EIA's liquefaction capacity file. Last verified by Enercast on Nov 27, 2026.
| Status | Commissioning | |
|---|---|---|
| Capacity | 2.57 Bcf/d stated FERC list figure | |
| Capacity, MTPA | 18.1 stated | |
| DOE non-FTA export authorization | 2.57 Bcf/d | |
| Trains | 3 | |
| Timing | T2 1H 2027 stated | |
| Sponsor | QatarEnergy 70% / ExxonMobil 30% | |
| Project type | New terminal | |
| Terminal | Golden Pass · observed feedgas, daily → | |
| Location | TX | |
| Region | US Gulf Coast | |
| Regulator | FERC (onshore terminal) | |
| FERC docket | CP14-517, CP20-459 | |
| Last verified | Nov 27, 2026 | all sources fetched |
Facts with no source beside them were compiled by Enercast from the documents listed under Sources when the project was first listed.
Capacity and timing are what the source states. None is measured or forecast by Enercast. How to read this page. The website and free subscribers get updates weekly. Pro subscribers get them daily.
Feed gas into the Golden Pass terminal is measured daily from pipeline postings on its LNG feedgas page: that is where a commissioning ramp shows up first.
Milestones
- First LNG · Train 1 stated
- First cargo · Train 1 stated
Trains
| Train | Bcf/d | Basis | Timing as stated | Note |
|---|---|---|---|---|
| Train 1 | 0.68 | EIA nominal | 1H2026 | EIA row 'Golden Pass Train 1E'; peak 0.795 Bcf/d; EIA file released 2025-06-30 |
| Train 2 | 0.68 | EIA nominal | 2H2026 | EIA row 'Golden Pass Train 2E'; peak 0.795 Bcf/d; EIA file released 2025-06-30 |
| Train 3 | 0.68 | EIA nominal | 1H2027 | EIA row 'Golden Pass Train 3E'; peak 0.795 Bcf/d; EIA file released 2025-06-30 |
From EIA’s U.S. liquefaction capacity file and FERC filings, as stated. EIA’s file is updated irregularly; the project’s own timing above is the more recent statement.
Change log
No changes since this project was first listed on Nov 25, 2026.
Sources
- Company, Mar 30, 2026: Golden Pass LNG: first LNG production
- Trade press, Jun 26, 2026: S&P 2026-06-26
- FERC, Nov 17, 2026: FERC LNG export terminals list as of 2026-11-17
- FERC, Nov 20, 2026: FERC eLibrary 20261120-3021 (CP14-517): Order/Opinion / Delegated Order
- DOE: DOE LNG Snapshot Sep 2026
- Company: Golden Pass LNG first LNG
- EIA, Jun 30, 2025: EIA U.S. Liquefaction Capacity file, release 2025-06-30
- EIA, Apr 22, 2026: EIA: Golden Pass ships first cargo
- EIA, Apr 23, 2026: EIA 2026-04-23