Offline today · gas day Nov 12
0.799Bcf/d
up 0.400 from Nov 11
bullish 0.399bearish 0.400
Outages in effect
15
3 with a posted volume · 12 without (flow data suggests ~0.029 Bcf/d more, est.)
Next 7 days
1 ending · 0 starting
0.000 Bcf/d due back · pipeline-posted dates
New capacity coming: 40.1 Bcf/d stated across 23 pipeline projects under construction, and 22.4 Bcf/d approved but not yet building. Next due: Bay Runner Pipeline (2.64 Bcf/d stated, 4Q26).
New Capacity tracker →

Today’s brief · gas day Nov 12

0.799 Bcf/d of pipeline capacity is offline on gas day Nov 12, up 0.400 from Nov 11, mostly because Sabine Pass Gillis station went offline (0.400). The largest are Sabine Pass Gillis station (0.400) and CGT Hampshire station (0.391). 12 more outages have no posted volume. Over the next 7 days, 1 outage is due back and nothing new is scheduled.

Largest outages now

  • Sabine Pass Gillis station0.400
    bearish · planned · until Nov 21
  • CGT Hampshire station0.391
    bullish · planned · until Nov 25
  • Tallgrass Energy Bertrand station0.008
    bullish · unplanned · no end date posted
  • Great Lakes Richfield~0.029 est.
    bullish · unplanned · until Dec 1
  • ANR UPDATED: CAPACITY REDUCTION Southwest Ma…no volume
    bullish · planned · until Dec 18
  • Colorado Interstate Gas Segment 164 Cheyenne Westno volume
    bearish · unplanned · until Dec 31
  • +9 more in the calendar below

Since Nov 11

  • Sabine Pass Gillis station0.400
    New · until Nov 21
  • NGPL Amarillo 2 Mainlineno volume
    New · until Nov 30

Next 7 days (to Nov 19)

  • Kinder Morgan Louisiana Pipeline CS 760no volume
    Due back · posted end Nov 12

Volumes are what the pipeline posted (or derived from a posted cap); “est.” marks an estimate from a drop in posted capacity. Dates are the pipeline’s own, not forecasts. Click any line for its notices.

Capacity offline by day

Quantified Bcf/d in effect each gas day, stacked by market side. Bars left of today are reconstructed from each event's posted window; dots mark what the ledger actually recorded that morning. Bars right of today are posted schedules, not forecasts.

Where capacity is offline

One marker per event in effect or scheduled, sized by Bcf/d and colored by market side; green rings are events lifted in the last seven days. Hollow markers are unquantified or ceiling-only. Markers sit at the compressor station, plant or terminal named in the notice where we have its location (HIFLD), otherwise on the pipeline’s line; dashed lines are schematic routes. Hover a marker for a summary and click it for the notices; hover a line to see the system, click it to filter the calendar.

Outage calendar

Click any bar for the event's notice chain and permalinks. Open-ended bars fade out at the right edge: the pipeline has not posted a return date.

Active (stated window) Active, until further notice Scheduled Lifted / expired Stale (no re-listing) bullish bearish basis-only Due back (day after posted end)

In-effect detail

Every event currently in effect, with the figure's basis. Ceiling-only postings show the remaining capacity, never a reduction, and are not in any total.

About this data One bar per outage event, built from posted critical notices; stated, derived and estimated figures are labeled, and only stated or derived reductions are totaled. How Capacity Offline works → Capacity Offline FAQ →