Plaquemines LNG Phase 2 (Blocks 10-18)

Venture Global · 1.88 Bcf/d stated · Commissioning

Plaquemines LNG Phase 2 (Blocks 10-18) is a set of new liquefaction trains at an existing terminal by Venture Global in LA. It is commissioning: producing first LNG, but not yet fully in commercial operation. Stated liquefaction capacity is 1.88 Bcf/d (FERC list figure). Trains: 18. Timing is stated as Phase 2 commercial deliveries mid-2027. FERC dockets CP17-66, CP22-92. Sources: FERC, the Department of Energy, trade press and EIA's liquefaction capacity file. Last verified by Enercast on Nov 27, 2026.

StatusCommissioning
Capacity1.88 Bcf/d stated FERC list figure
DOE non-FTA authorisation: 3.85 (whole terminal) Bcf/d
Capacity, MTPANot stated—
Trains18
TimingPhase 2 commercial deliveries mid-2027 stated
SponsorVenture Global
Project typeNew trains at existing terminal
TerminalPlaquemines · observed feedgas, daily →
LocationLA
RegionUS Gulf Coast
RegulatorFERC (onshore terminal)
FERC docketCP17-66, CP22-92
Last verifiedNov 27, 2026all sources fetched

Facts with no source beside them were compiled by Enercast from the documents listed under Sources when the project was first listed.

Capacity and timing are what the source states. None is measured or forecast by Enercast. How to read this page. The website and free subscribers get updates weekly. Pro subscribers get them daily.

Feed gas into the Plaquemines terminal is measured daily from pipeline postings on its LNG feedgas page: that is where a commissioning ramp shows up first.

Milestones

No dated milestones recorded yet. They are added as FERC orders and letters, DOE authorizations and the sponsor’s own announcements (FID, first LNG, first cargo) appear.

Trains

TrainBcf/dBasisTiming as statedNote
Trains 19-361.32EIA nominal2025-09EIA row 'Plaquemines LNG Phase 2 Trains 19-36F'; peak 1.581 Bcf/d; EIA file released 2025-06-30

From EIA’s U.S. liquefaction capacity file and FERC filings, as stated. EIA’s file is updated irregularly; the project’s own timing above is the more recent statement.

Change log

No changes since this project was first listed on Nov 25, 2026.