CP2 LNG Expansion

Venture Global · 1.62 Bcf/d stated · Applied

CP2 LNG Expansion is a set of new liquefaction trains at an existing terminal by Venture Global in LA. It has an application pending and is not yet approved. Stated liquefaction capacity is 1.62 Bcf/d (FERC list figure), or 10 MTPA. Timing is stated as FID early 2027. FERC docket CP26-530. Sources: FERC and trade press. Last verified by Enercast on Nov 27, 2026.

StatusApplied
Capacity1.62 Bcf/d stated FERC list figure
Capacity, MTPA10 stated
Trains——
TimingFID early 2027 stated
SponsorVenture Global
Project typeNew trains at existing terminal
Terminal——
LocationLA
RegionUS Gulf Coast
RegulatorFERC (onshore terminal)
FERC docketCP26-530
Last verifiedNov 27, 2026all sources fetched

Facts with no source beside them were compiled by Enercast from the documents listed under Sources when the project was first listed.

Capacity and timing are what the source states. None is measured or forecast by Enercast. How to read this page. The website and free subscribers get updates weekly. Pro subscribers get them daily.

Milestones

No dated milestones recorded yet. They are added as FERC orders and letters, DOE authorizations and the sponsor’s own announcements (FID, first LNG, first cargo) appear.

Change log

No changes since this project was first listed on Nov 25, 2026.