Lake Charles LNG is a conversion of an LNG import terminal to export by Energy Transfer in LA. It is on hold. Stated liquefaction capacity is 2.27 Bcf/d (FERC list figure), or 16.5 MTPA. FERC docket CP14-120. Sources: FERC and trade press. Last verified by Enercast on Nov 27, 2026.
| Status | On hold | |
|---|---|---|
| Capacity | 2.27 Bcf/d stated FERC list figure | |
| Capacity, MTPA | 16.5 stated | |
| DOE non-FTA export authorization | 2.33 Bcf/d | |
| Trains | — | — |
| Timing | in-service deadline 2031 (FERC extension) stated | |
| Sponsor | Energy Transfer | |
| Project type | Conversion (import to export) | |
| Terminal | — | — |
| Location | LA | |
| Region | US Gulf Coast | |
| Regulator | FERC (onshore terminal) | |
| FERC docket | CP14-120 | |
| Last verified | Nov 27, 2026 | all sources fetched |
Facts with no source beside them were compiled by Enercast from the documents listed under Sources when the project was first listed.
Capacity and timing are what the source states. None is measured or forecast by Enercast. How to read this page. The website and free subscribers get updates weekly. Pro subscribers get them daily.
Milestones
No dated milestones recorded yet. They are added as FERC orders and letters, DOE authorizations and the sponsor’s own announcements (FID, first LNG, first cargo) appear.
Change log
No changes since this project was first listed on Nov 25, 2026.
Sources
- Trade press, Dec 18, 2025: S&P 2025-12-18
- FERC, Nov 17, 2026: FERC LNG export terminals list as of 2026-11-17