Every status, date and capacity here comes from a named source: a FERC filing, the sponsor’s own page or investor material, or EIA’s project tracker.
Capacity is the figure the sponsor or regulator states, and in-service timing is in the source’s own words. Enercast checks the sources every night and a person approves every change before it appears here. 52 projects are marked EIA only: they have not yet been checked against FERC or the sponsor. How this page works.
Stated capacity by stated in-service year
Bcf/d of stated capacity, stacked by project status, in the year each project’s sponsor (or EIA, where that is the only source) says it will enter service, from 2026 on. Click a status to hide or show it. This is what sponsors have said, added up, not a forecast: projects slip, phase in over time, and some overlap or feed one another, so the totals overstate net new takeaway. Announced and pre-filing projects may never be built.
View these numbers as a table
| Status | 2026 | 2027 | 2028 | 2029 | 2030 | 2031 | No date |
|---|---|---|---|---|---|---|---|
| In service | 8.6 | — | — | — | — | — | — |
| Partial service | 2.0 | 2.3 | 0.2 | — | — | — | — |
| Under construction | 3.6 | 14.9 | 12.9 | 1.5 | — | 2.6 | — |
| Approved | 0.2 | 2.5 | 2.0 | 7.4 | 4.0 | 1.4 | 4.9 |
| Applied | 0.7 | 0.5 | 8.2 | 6.6 | — | 6.2 | — |
| Pre-filing | — | — | 0.9 | 4.9 | 0.6 | — | — |
| Announced | — | 0.3 | 0.4 | 10.6 | 6.0 | — | 3.5 |
| On hold | — | — | — | — | — | — | 11.3 |
| All statuses | 15.2 | 20.6 | 24.7 | 31.0 | 10.6 | 10.1 | 19.7 |
Changed in the last 7 days
3 projects entered service (4.2 Bcf/d stated); 1 project moved into construction or partial service (1.2 Bcf/d stated); 2 other status changes; 30 in-service date updates; 5 capacity revisions (net +1.1 Bcf/d stated).
| Project | Bcf/d | Changed | Previous | Updated |
|---|---|---|---|---|
| Kosciusko Junction Pipeline Project | 1.18 | Status | Approved | Under construction · in service September 2028 · FERC |
| Nueva Era Dos Pipeline Project | 1.00 | Status | Applied | Approved · in service 2027 · FERC |
| Blackcomb Pipeline | 2.50 | Status | Under construction | In service · Company |
| CCPL Expansion Project (Corpus Christi Stage IV) | 2.75 | Status | Pre-filing | Applied · in service 2031 · Company |
| Gillis Access Project Extension | 1.40 | Status | Approved | In service · Company |
| Ridgeline Expansion Project | 0.30 | Status | Under construction | In service · Company |
| Kosciusko Junction Pipeline Project | 1.18 | Milestone | — | Construction authorized, Nov 6, 2026 |
| Pulaski Expansion Project | 0.26 | Milestone | — | FERC approval, Oct 15, 2026 |
| Ridgeline Expansion Project | 0.30 | Milestone | — | Partial service, Oct 30, 2026 |
| Borealis Project | 2.00 | In-service date | 2030 | 4Q 2029 · Company |
| Constitution Pipeline (Revival) | 0.65 | In-service date | 2028 | 4Q 2028 · Company |
| Dearborn County Lateral | 0.27 | In-service date | 2028 | Q2 2028 · Company |
| Desert Southwest Expansion Project | 2.30 | In-service date | 2029 | By Q4 2029 · Company |
| Driftwood Line 200 and 300 Project | 3.10 | In-service date | 2028 | 2Q 2028 · Company |
Show the other 30 changes
| Project | Bcf/d | Changed | Previous | Updated |
|---|---|---|---|---|
| Eiger Express Pipeline | 3.70 | In-service date | 2028 | Mid-2028 · Company |
| Elba Express Bridge Project (EEBP) | 0.33 | In-service date | 2030 | second quarter of 2030 · Company |
| Florida Gas Transmission Phase 9 Expansion | 0.53 | In-service date | 2028 | Q4 2028 · Company |
| Guardian Pipeline Project | 0.54 | In-service date | 2028 | November 2028 · Company |
| Heartland Project | 0.47 | In-service date | 2027 | Q4 2027 · Company |
| Hugh Brinson Pipeline | 2.30 | In-service date | 2026 | Q1 2027 · Company |
| Kosciusko Junction Pipeline Project | 1.18 | In-service date | 2029 | September 2028 · Company |
| Maysville Expansion Project | 0.34 | In-service date | 2029 | Q1 2029 · Company |
| Mississippi Crossing (MSX) | 2.10 | In-service date | 2028 | as early as the second quarter of 2028 · Company |
| North Extension Project | 0.21 | In-service date | 2028 | fourth quarter of 2028 · Company |
| Northeast Supply Enhancement Project | 0.40 | In-service date | 2027 | Q4 2027 · Company |
| Northwoods Project | 0.39 | In-service date | 2029 | Q4 2029 · Company |
| Parks Line Upgrade and Sorrento Station Project (PLUSS Project) | 0.24 | In-service date | 2027 | Q1 2028 · Company |
| Pelican Pipeline | 2.50 | In-service date | 2027 | first half of 2027 · Company |
| Pelican Thrasher Lateral | 2.50 | In-service date | 2029 | first half of 2029 · Company |
| Pulaski Expansion Project | 0.26 | In-service date | 2029 | Q1 2029 · Company |
| Ridgeline Expansion Project | 0.30 | In-service date | 2026 | November 2026 · Company |
| Silver Spur Project | 0.28 | In-service date | 2030 | 2Q 2030 · Company |
| Southeast Supply Enhancement Project | 1.60 | In-service date | 2027 | 3Q 2027 · Company |
| System Expansion 4 (SSE4) Project | 1.32 | In-service date | 2028 | fourth quarter of 2029 · Company |
| Texas Access Project | 1.30 | In-service date | 2028 | second quarter of 2028 · Company |
| Texas-Arkansas Power Project (TAPP) | 0.40 | In-service date | 2028 | November 1, 2028 · Company |
| Traverse Pipeline | 2.50 | In-service date | 2027 | 2H27 · Company |
| Trident Intrastate Pipeline | 2.00 | In-service date | 2027 | fourth quarter of 2028 · Company |
| Bay Runner Pipeline | 2.64 | In-service date | 2026 | 4Q26 · Company |
| Crossroads Expansion Project | 1.40 | Capacity | 1.5 Bcf/d | 1.4 Bcf/d (-0.10) · Company |
| Driftwood Line 200 and 300 Project | 3.10 | Capacity | 2.4 Bcf/d | 3.1 Bcf/d (+0.70) · Company |
| Hugh Brinson Pipeline | 2.30 | Capacity | 2.2 Bcf/d | 2.3 Bcf/d (+0.10) · Company |
| Texas Gateway Project | 1.80 | Capacity | 1.45 Bcf/d | 1.8 Bcf/d (+0.35) · Company |
| Traverse Pipeline | 2.50 | Capacity | 2.4 Bcf/d | 2.5 Bcf/d (+0.10) · Company |
Bcf/d is each project’s stated capacity. “Previous” and “Updated” are the values before and after the change Enercast recorded this week; the source is shown beside the new value.
Projects
99 projects
| Project | Bcf/d stated | Status | Stated in-service | Verified |
|---|---|---|---|---|
| Louisiana Connector (Port Arthur Pipeline)EIA onlyPort Arthur Pipeline LLC · LA, TX | 2.00 | Partial service | 2026 | Nov 10, 2026 |
| Hugh Brinson PipelineEnergy Transfer LP (via Hugh Brinson Pipeline LLC) · TX | 2.30 | Partial service | Q1 2027 | Nov 11, 2026 |
| Parks Line Upgrade and Sorrento Station Project (PLUSS Project)Gulf South Pipeline Company, LLC · LA | 0.24 | Partial service | Q1 2028 | Nov 10, 2026 |
| Bay Runner PipelineWhiteWater Midstream · TX | 2.64 | Under construction | 4Q26 | Nov 11, 2026 |
| Rover-Bulger CS and Harmon Creek MS ExpansionRover Pipeline LLC (Energy Transfer) · PA | 0.40 | Under construction | 2026 | Nov 10, 2026 |
| Bakken xPress ProjectEIA onlyWyoming Interstate Company · ND, WY | 0.30 | Under construction | 2026 | Nov 10, 2026 |
| TTC Connector Pipeline ProjectTTC Connector, LLC · TX | 0.30 | Under construction | 2026 | Nov 10, 2026 |
| Pelican PipelineWhiteWater Midstream · LA | 2.50 | Under construction | first half of 2027 | Nov 11, 2026 |
| Southeast Supply Enhancement ProjectTranscontinental Gas Pipeline · VA, NC, SC, GA, AL | 1.60 | Under construction | 3Q 2027 | Nov 10, 2026 |
| Blackfin PipelineEIA onlyWhiteWater Midstream · TX | 3.50 | Under construction | 2027 | Nov 11, 2026 |
| Golden Pass LateralEIA onlyGolden Pass LNG Terminal LLC · TX | 2.60 | Under construction | 2027 | Nov 10, 2026 |
| Traverse PipelineWPC JV (WhiteWater/MPLX/Enbridge) + Targa · TX | 2.50 | Under construction | 2H27 | Nov 11, 2026 |
| CP Express Pipeline ProjectVenture Global · TX, LA | 1.80 | Under construction | 2027 | Nov 10, 2026 |
| Northeast Supply Enhancement ProjectTranscontinental Gas Pipe Line Company, LLC · PA, NJ, NY | 0.40 | Under construction | Q4 2027 | Nov 10, 2026 |
| Driftwood Line 200 and 300 ProjectDriftwood Pipeline LLC · LA | 3.10 | Under construction | 2Q 2028 | Nov 10, 2026 |
| Mississippi Crossing (MSX)Tennessee Gas Pipeline Co., LLC (Kinder Morgan) · MS, AL | 2.10 | Under construction | as early as the second quarter of 2028 | Nov 10, 2026 |
| Southeast Compression Utility and Reliability Expansion (SECURE) ProjectGulf South Pipeline Company, LLC · LA, MS | 0.28 | Under construction | Q2 2028 | Nov 10, 2026 |
| Eiger Express PipelineWhiteWater Midstream · TX | 3.70 | Under construction | Mid-2028 | Nov 11, 2026 |
| Kosciusko Junction Pipeline ProjectGulf South Pipeline Company, LLC ; Texas Gas Transmission. LLC · MS | 1.18 | Under construction | September 2028 | Nov 10, 2026 |
| Trident Intrastate PipelineKinder Morgan · TX | 2.00 | Under construction | fourth quarter of 2028 | Nov 11, 2026 |
| Mountain Valley Pipeline Southgate AmendmentEIA onlyMountain Valley Pipeline, LLC · VA, NC | 0.55 | Under construction | 2028 | Nov 10, 2026 |
| Corpus Christi Stage III PipelineEIA onlyCheniere Energy Corpus Christi · TX | 1.53 | Under construction | 2029 | Nov 10, 2026 |
| Pipeline Modifications Project (Lake Charles LNG)EIA onlyTrunkline Gas · AR, MS, LA | 2.60 | Under construction | 2031 | Nov 10, 2026 |
| Shippingport Lateral ProjectEIA onlyNational Fuel Gas Supply Corporation · PA | 0.20 | Approved | 2026 | Nov 10, 2026 |
| Holbrook Expansion ProjectEIA onlyCameron Interstate Pipeline · LA | 1.08 | Approved | 2027 | Nov 10, 2026 |
| Nueva Era Dos Pipeline ProjectNueva Era Pipeline LLC · TX, MX | 1.00 | Approved | 2027 | Nov 10, 2026 |
| Heartland ProjectANR Pipeline Company · IL, WI | 0.47 | Approved | Q4 2027 | Nov 10, 2026 |
| Bull Run ExtensionEIA onlyTarga Resources · TX | 0.75 | Approved | 2028 | Nov 10, 2026 |
| Appalachian Reliability ProjectEastern Gas Transmission and Storage · PA, OH | 0.55 | Approved | 2028 | Nov 10, 2026 |
| Texas Connector-Port Arthur PipelineEIA onlySempra Infrastructure (Port Arthur Pipeline) · TX | 0.49 | Approved | 2028 | Nov 10, 2026 |
| Ameren-EMRT Big Hollow ProjectEnable Mississippi River Transmission LLC · IL, MO | 0.20 | Approved | 2028 | Nov 10, 2026 |
| Pulaski Expansion ProjectColumbia Gulf Transmission · KY | 0.26 | Approved | Q1 2029 | Nov 10, 2026 |
| Alaska LNG Pipeline (Nikiski)EIA only8 Star Alaska LLC · AK | 3.30 | Approved | 2029 | Nov 10, 2026 |
| Mustang Express PipelineEIA onlyArm Energy Holdings LLC · TX | 2.50 | Approved | 2029 | Nov 11, 2026 |
| System Expansion 4 (SSE4) ProjectSouthern Natural Gas Co., LLC & Elba Express Co., LLC (Kinder Morgan) · MS, AL, GA, SC | 1.32 | Approved | fourth quarter of 2029 | Nov 10, 2026 |
| Saguaro Connector PipelineOneok Westex Transmission, LLC · TX, MX | 2.80 | Approved | 2030 | Nov 10, 2026 |
| South Mississippi ProjectEnergy Transfer Interstate Holdings, LLC · LA, MS | 1.20 | Approved | 2030 | Nov 11, 2026 |
| Lake Charles Expansion (Magnolia LNG)EIA onlyKinder Morgan Louisiana Pipeline LLC · LA | 1.36 | Approved | 2031 | Nov 10, 2026 |
| Rio Bravo Pipeline ProjectEIA onlyRio Bravo Pipeline Company (Enbridge) · TX | 4.50 | Approved | Not stated | Nov 10, 2026 |
| Green Chile ProjectEIA onlyEnergy Transfer (Transwestern) · NM | 0.40 | Approved | Not stated | Nov 10, 2026 |
| Dude Lateral ProjectEIA onlyDouble E Pipeline, LLC · NM | 0.40 | Applied | 2026 | Nov 10, 2026 |
| Transco Wharton West ProjectEIA onlyTranscontinental Gas Pipe Line (Williams) · TX | 0.31 | Applied | 2026 | Nov 11, 2026 |
| Central Mainline Corridor ExpansionEIA onlyNorthern Natural Gas Co. · NE, IA | 0.54 | Applied | 2027 | Nov 10, 2026 |
| Texas Access ProjectKinder Morgan Louisiana Pipeline LLC · TX, LA | 1.30 | Applied | second quarter of 2028 | Nov 10, 2026 |
| Dearborn County LateralTexas Gas Transmission LLC · IN, KY, OH | 0.27 | Applied | Q2 2028 | Nov 10, 2026 |
| Guardian Pipeline ProjectDT Midstream · WI, IL | 0.54 | Applied | November 2028 | Nov 10, 2026 |
| Texas-Arkansas Power Project (TAPP)Natural Gas Pipeline Company of America LLC · TX, AR | 0.40 | Applied | November 1, 2028 | Nov 10, 2026 |
| Franklin Farms ProjectEIA onlyETC Tiger Pipeline, LLC · LA | 1.00 | Applied | 2028 | Nov 10, 2026 |
| Double E Pipeline ExpansionDouble E Pipeline, LLC · NM, TX | 0.90 | Applied | 2028 | Nov 10, 2026 |
| Forza PipelineEIA onlyForza Pipeline LLC & Bull Run Pipeline LLC (Targa Resources) · NM, TX | 0.75 | Applied | 2028 | Nov 10, 2026 |
| Constitution Pipeline (Revival)Constitution Pipeline Co. LLC · PA, NY | 0.65 | Applied | 4Q 2028 | Nov 10, 2026 |
| Wright Interconnect ProjectEIA onlyIroquois Gas Transmission System, L.P. · NY | 0.65 | Applied | 2028 | Nov 10, 2026 |
| MVP Boost ExpansionEIA onlyMountain Valley Pipeline, LLC · WV, VA | 0.60 | Applied | 2028 | Nov 10, 2026 |
| Florida Gas Transmission Phase 9 ExpansionFlorida Gas Transmission Company, LLC · FL | 0.53 | Applied | Q4 2028 | Nov 10, 2026 |
| Vector Pipeline ExpansionEIA onlyVector Pipeline (DT Midstream / Enbridge JV) · IN, MI, IL | 0.40 | Applied | 2028 | Nov 11, 2026 |
| North Extension ProjectNatural Gas Pipeline Company of America LLC · IA, IL, WI | 0.21 | Applied | fourth quarter of 2028 | Nov 10, 2026 |
| Maysville Expansion ProjectColumbia Gulf Transmission · KY | 0.34 | Applied | Q1 2029 | Nov 10, 2026 |
| Cloud Connector PipelineEIA onlyCloud Connector, LLC · LA | 4.50 | Applied | 2029 | Nov 11, 2026 |
| Texas Gateway ProjectGulf South Pipeline Co. LLC · TX, LA | 1.80 | Applied | 2029 | Nov 10, 2026 |
| CCPL Expansion Project (Corpus Christi Stage IV)Cheniere Corpus Christi Pipeline, L.P. · TX | 2.75 | Applied | 2031 | Nov 10, 2026 |
| Sabine Crossing PipelineEIA onlyCheniere Energy (Sabine Crossing Pipeline, LLC) · TX, LA | 2.50 | Applied | 2031 | Nov 10, 2026 |
| CTPL Expansion ProjectEIA onlyCheniere Creole Trail Pipeline, L.P · LA | 0.93 | Applied | 2031 | Nov 10, 2026 |
| Great Basin 2028 Expansion ProjectEIA onlyGreat Basin Gas Transmission · NV | 0.95 | Pre-filing | 2028 | Nov 10, 2026 |
| Desert Southwest Expansion ProjectTranswestern · NM, AZ | 2.30 | Pre-filing | By Q4 2029 | Nov 10, 2026 |
| Bakken East Pipeline ProjectEIA onlyWBI Energy Transmission · ND | 1.40 | Pre-filing | 2029 | Nov 10, 2026 |
| Yuma Pipeline ProjectEIA onlyLED Enterprises LLC · AZ | 0.80 | Pre-filing | 2029 | Nov 10, 2026 |
| Northwoods ProjectANR Pipeline Company · MI, WI | 0.39 | Pre-filing | Q4 2029 | Nov 10, 2026 |
| Elba Express Bridge Project (EEBP)Elba Express Company LLC · GA, SC | 0.33 | Pre-filing | second quarter of 2030 | Nov 10, 2026 |
| Silver Spur ProjectNorthwest Pipeline LLC · NV, ID | 0.28 | Pre-filing | 2Q 2030 | Nov 10, 2026 |
| Aspire Energy ExpressEIA onlyAspire Energy Express LLC · OH | 0.30 | Announced | 2027 | Nov 11, 2026 |
| Clarington ConnectorEIA onlyEQT Corp. · OH, PA | 0.40 | Announced | 2028 | Nov 11, 2026 |
| Pelican Thrasher LateralWhiteWater Midstream · LA | 2.50 | Announced | first half of 2029 | Nov 11, 2026 |
| Delta Access PipelineEIA onlyWilliams · LA | 2.25 | Announced | 2029 | Nov 11, 2026 |
| Solitude PipelineEIA onlyWhiteWater Midstream · TX | 2.25 | Announced | 2029 | Nov 11, 2026 |
| Borealis ProjectTexas Gas Transmission, LLC · OH, KY | 2.00 | Announced | 4Q 2029 | Nov 11, 2026 |
| Intensity Pipeline ProjectEIA onlyIntensity Infrastructure Partners · ND | 1.10 | Announced | 2029 | Nov 11, 2026 |
| Dalton Lateral Expansion II ProjectEIA onlyTranscontinental Gas Pipe Line Company, LLC · GA | 0.46 | Announced | 2029 | Nov 11, 2026 |
| Solitude II PipelineEIA onlyWhiteWater Midstream · TX | 2.25 | Announced | 2030 | Nov 11, 2026 |
| West Texas ExpressEIA onlyEnbridge · TX | 2.00 | Announced | 2030 | Nov 11, 2026 |
| Crossroads Expansion ProjectCrossroads Pipeline Co. (TC Energy) · OH, IN | 1.40 | Announced | 2030 | Nov 11, 2026 |
| Algonquin Project BeaconEIA onlyAlgonquin Gas Transmission LLC · NY, CT, MA, RI | 0.30 | Announced | 2030 | Nov 11, 2026 |
| Carthage CrossingEIA onlyGulf South Pipeline Co. LLC · TX, LA | 2.00 | Announced | Not stated | Nov 11, 2026 |
| Midwestern Gas Transmission ExpansionEIA onlyMidwestern Gas Transmission Co. (DT Midstream) · IL, TN | 1.50 | Announced | Not stated | Nov 11, 2026 |
| Westbound Compression Expansion ProjectEIA onlyWilliams (MountainWest Overthrust) · WY | 0.33 | In service | In service Dec 1, 2025 | Nov 11, 2026 |
| Ridgeline Expansion ProjectEast Tennessee Nat Gas Co · TN | 0.30 | In service | In service | Nov 10, 2026 |
| Blackcomb PipelineWhiteWater Midstream · TX | 2.50 | In service | In service | Nov 11, 2026 |
| Golden Pass LNG Bidirectional PipelineEIA onlyGolden Pass Pipeline LLC · LA, TX | 2.50 | In service | In service Jan 27, 2026 | Nov 11, 2026 |
| Gator Express UprateVenture Global Gator Express LLC · LA | 0.63 | In service | In service Sep 10, 2026 | Nov 11, 2026 |
| Gulf Coast Express ExpansionEIA onlyKinder Morgan Energy Partners · TX | 0.57 | In service | In service | Nov 11, 2026 |
| Texas-Louisiana Expansion ProjectNatural Gas Pipeline Company of America LLC · TX, LA | 0.47 | In service | In service Jul 10, 2026 | Nov 11, 2026 |
| Cumberland ProjectEIA onlyTennessee Gas Pipeline Co · TN | 0.24 | In service | In service May 26, 2026 | Nov 11, 2026 |
| Gillis Access Project ExtensionTC Energy · LA | 1.40 | In service | In service | Nov 10, 2026 |
| Driftwood LNG PipelineEIA onlyDriftwood Pipeline LLC (Williams) · LA | 4.00 | On hold | Not stated | Nov 10, 2026 |
| Apex PipelineEIA onlyTarga Resources · TX | 2.00 | On hold | Not stated | Nov 11, 2026 |
| DeLa Express ProjectEIA onlyDeLa Express LLC · TX | 2.00 | On hold | Not stated | Nov 10, 2026 |
| Delta Express Pipeline ProjectEIA onlyDelta Express Pipeline LLC (Venture Global LNG) · LA, MS | 2.00 | On hold | Not stated | Nov 10, 2026 |
| Tioga to Emerson ProjectEIA onlyWBI Energy Transmission · ND, MN | 0.60 | On hold | Not stated | Nov 11, 2026 |
| Greater Philadelphia ExpansionEIA onlyTexas Eastern Transmission, LP (subsidiary of Enbridge) · PA | 0.47 | On hold | Not stated | Nov 10, 2026 |
| NGPL Gulf Coast Southbound Project (Phase III)EIA onlyNat Gas P L Co of America · IA, IL, MO, AR, TX | 0.26 | On hold | Not stated | Nov 11, 2026 |