MVP Boost Expansion is a natural gas pipeline expansion project by Mountain Valley Pipeline, LLC in WV, VA. It has an application pending and is not yet approved. Stated capacity is 0.6 Bcf/d. In-service timing is listed by EIA as 2028. FERC docket CP26-14. Source: EIA's pipeline project tracker. Last verified by Enercast on Nov 10, 2026.
EIA only. So far the only source for this project is EIA’s pipeline project tracker, which lists a year, not a date, and can lag. Nothing here has yet been checked against a FERC filing or the sponsor.
| Status | Applied | EIA, dated Aug 6, 2026 |
|---|---|---|
| Capacity | 0.6 Bcf/d stated | EIA, dated Aug 6, 2026 |
| In-service timing | 2028 EIA-listed year | EIA, dated Aug 6, 2026 |
| Operator | Mountain Valley Pipeline, LLC | EIA, dated Aug 6, 2026 |
| Project type | Expansion | EIA, dated Aug 6, 2026 |
| States | WV, VA | EIA, dated Aug 6, 2026 |
| Length | — | EIA, dated Aug 6, 2026 |
| Jurisdiction | Interstate (FERC-regulated) · FERC | EIA, dated Aug 6, 2026 |
| FERC docket | CP26-14 | EIA, dated Aug 6, 2026 |
| Demand served | Power | EIA, dated Aug 6, 2026 |
| Last verified | Nov 10, 2026 | all sources fetched |
Capacity and in-service timing are what the source states. None is measured or forecast by Enercast. How to read this page.
Milestones
No dated milestones recorded yet. They are added as FERC orders, construction authorizations and in-service notices appear.
Change log
No changes since this project was first listed on Nov 10, 2026.