Enercast — at the moment it matters
Enercast  /  New Capacity  /  Northwoods Project

Northwoods Project

ANR Pipeline Company · 0.39 Bcf/d stated · Pre-filing

Northwoods Project is a natural gas pipeline expansion project by ANR Pipeline Company in MI, WI. It is in FERC's pre-filing process. Stated capacity is 0.39 Bcf/d. In-service timing is stated as Q4 2029. FERC docket PF26-6. Sources: the sponsor's public material and EIA's pipeline project tracker. Last verified by Enercast on Nov 10, 2026.

StatusPre-filingEIA, dated Apr 21, 2026
Capacity0.39 Bcf/d statedEIA, dated Apr 21, 2026
In-service timingQ4 2029 company-statedCompany, read Nov 11, 2026
OperatorANR Pipeline CompanyEIA, dated Apr 21, 2026
Project typeExpansionEIA, dated Apr 21, 2026
StatesMI, WIEIA, dated Apr 21, 2026
Length92 milesEIA, dated Apr 21, 2026
JurisdictionInterstate (FERC-regulated) · FERCEIA, dated Apr 21, 2026
FERC docketPF26-6EIA, dated Apr 21, 2026
Demand servedElectricEIA, dated Apr 21, 2026
Last verifiedNov 10, 2026all sources fetched

Capacity and in-service timing are what the source states. None is measured or forecast by Enercast. How to read this page.

Milestones

No dated milestones recorded yet. They are added as FERC orders, construction authorizations and in-service notices appear.

Change log

RecordedFieldChangeSource
Nov 11, 2026Stated in-service2029 → Q4 2029Company, read Nov 11, 2026

“Recorded” is the day Enercast approved the change, not the day it happened.

Sources

← All new capacity projects