Enercast — at the moment it matters
Enercast  /  New Capacity  /  Blackfin Pipeline

Blackfin Pipeline

WhiteWater Midstream · 3.5 Bcf/d stated · Under construction

Blackfin Pipeline is a new natural gas pipeline project by WhiteWater Midstream in TX. It is under construction. Stated capacity is 3.5 Bcf/d. In-service timing is listed by EIA as 2027. Source: EIA's pipeline project tracker. Last verified by Enercast on Nov 11, 2026.

EIA only. So far the only source for this project is EIA’s pipeline project tracker, which lists a year, not a date, and can lag. Nothing here has yet been checked against a FERC filing or the sponsor.

StatusUnder constructionEIA, dated Jul 10, 2025
Capacity3.5 Bcf/d statedEIA, dated Jul 10, 2025
In-service timing2027 EIA-listed yearEIA, dated Jul 10, 2025
OperatorWhiteWater MidstreamEIA, dated Jul 10, 2025
Project typeNew PipelineEIA, dated Jul 10, 2025
StatesTXEIA, dated Jul 10, 2025
Length193 milesEIA, dated Jul 10, 2025
JurisdictionIntrastate · TX RRCEIA, dated Jul 10, 2025
State permitT4-10453EIA, dated Jul 10, 2025
Demand servedLNG/OtherEIA, dated Jul 10, 2025
Last verifiedNov 11, 2026all sources fetched

Capacity and in-service timing are what the source states. None is measured or forecast by Enercast. How to read this page.

Milestones

No dated milestones recorded yet. They are added as FERC orders, construction authorizations and in-service notices appear.

Change log

No changes since this project was first listed on Nov 10, 2026.