Green Chile Project is a natural gas pipeline lateral project by Energy Transfer (Transwestern) in NM. It is approved but not yet under construction. Stated capacity is 0.4 Bcf/d. FERC docket CP26-80. Source: EIA's pipeline project tracker. Last verified by Enercast on Nov 10, 2026.
EIA only. So far the only source for this project is EIA’s pipeline project tracker, which lists a year, not a date, and can lag. Nothing here has yet been checked against a FERC filing or the sponsor.
| Status | Approved | EIA, dated Sep 4, 2026 |
|---|---|---|
| Capacity | 0.4 Bcf/d stated | EIA, dated Sep 4, 2026 |
| In-service timing | Not stated | — |
| Operator | Energy Transfer (Transwestern) | EIA, dated Sep 4, 2026 |
| Project type | Lateral | EIA, dated Sep 4, 2026 |
| States | NM | EIA, dated Sep 4, 2026 |
| Length | 17 miles | EIA, dated Sep 4, 2026 |
| Jurisdiction | Interstate (FERC-regulated) · FERC | EIA, dated Sep 4, 2026 |
| FERC docket | CP26-80 | EIA, dated Sep 4, 2026 |
| Demand served | Power / AI data center (Project Jupiter) | EIA, dated Sep 4, 2026 |
| Last verified | Nov 10, 2026 | all sources fetched |
Capacity and in-service timing are what the source states. None is measured or forecast by Enercast. How to read this page.
Milestones
No dated milestones recorded yet. They are added as FERC orders, construction authorizations and in-service notices appear.
Change log
No changes since this project was first listed on Nov 10, 2026.