Constitution Pipeline (Revival) is a new natural gas pipeline project by Constitution Pipeline Co. LLC in PA, NY. It has an application pending and is not yet approved. Stated capacity is 0.65 Bcf/d. In-service timing is stated as 4Q 2028. FERC docket CP13-499. Sources: the sponsor's public material and EIA's pipeline project tracker. Last verified by Enercast on Nov 10, 2026.
| Status | Applied | EIA, dated Apr 21, 2026 |
|---|---|---|
| Capacity | 0.65 Bcf/d stated | EIA, dated Apr 21, 2026 |
| In-service timing | 4Q 2028 company-stated | Company, read Nov 11, 2026 |
| Operator | Constitution Pipeline Co. LLC | EIA, dated Apr 21, 2026 |
| Project type | New Pipeline | EIA, dated Apr 21, 2026 |
| States | PA, NY | EIA, dated Apr 21, 2026 |
| Length | 125 miles | EIA, dated Apr 21, 2026 |
| Jurisdiction | Interstate (FERC-regulated) · FERC | EIA, dated Apr 21, 2026 |
| FERC docket | CP13-499 | EIA, dated Apr 21, 2026 |
| Demand served | LDC | EIA, dated Apr 21, 2026 |
| Last verified | Nov 10, 2026 | all sources fetched |
Capacity and in-service timing are what the source states. None is measured or forecast by Enercast. How to read this page.
Milestones
No dated milestones recorded yet. They are added as FERC orders, construction authorizations and in-service notices appear.
Change log
| Recorded | Field | Change | Source |
|---|---|---|---|
| Nov 11, 2026 | Stated in-service | 2028 → 4Q 2028 | Company, read Nov 11, 2026 |
“Recorded” is the day Enercast approved the change, not the day it happened.
Sources
- Company: Williams: Constitution Pipeline project page“4Q 2026 Target FERC Certificate Reinstated 4Q 2028 Target Pipeline In- Service”
- EIA: EIA Natural Gas Pipeline Projects, release 2026-11-04: Constitution Pipeline (Revival)