Enercast — at the moment it matters
Enercast  /  New Capacity  /  Louisiana Connector (Port Arthur Pipeline)

Louisiana Connector (Port Arthur Pipeline)

Port Arthur Pipeline LLC · 2 Bcf/d stated · Partial service

Louisiana Connector (Port Arthur Pipeline) is a new natural gas pipeline project by Port Arthur Pipeline LLC in LA, TX. It is partly in service, with the rest under construction. Stated capacity is 2 Bcf/d. In-service timing is listed by EIA as 2026. FERC dockets CP18-7, CP20-21, CP23-513. Source: EIA's pipeline project tracker. Last verified by Enercast on Nov 10, 2026.

EIA only. So far the only source for this project is EIA’s pipeline project tracker, which lists a year, not a date, and can lag. Nothing here has yet been checked against a FERC filing or the sponsor.

StatusPartial serviceEIA, dated Jul 6, 2026
Capacity2 Bcf/d statedEIA, dated Jul 6, 2026
In-service timing2026 EIA-listed yearEIA, dated Jul 6, 2026
OperatorPort Arthur Pipeline LLCEIA, dated Jul 6, 2026
Project typeNew PipelineEIA, dated Jul 6, 2026
StatesLA, TXEIA, dated Jul 6, 2026
Length72 milesEIA, dated Jul 6, 2026
JurisdictionInterstate (FERC-regulated) · FERCEIA, dated Jul 6, 2026
FERC docketCP18-7, CP20-21, CP23-513EIA, dated Jul 6, 2026
Demand servedLNGEIA, dated Jul 6, 2026
Last verifiedNov 10, 2026all sources fetched

Capacity and in-service timing are what the source states. None is measured or forecast by Enercast. How to read this page.

Milestones

No dated milestones recorded yet. They are added as FERC orders, construction authorizations and in-service notices appear.

Change log

No changes since this project was first listed on Nov 10, 2026.