TVA/TGP MAGNOLIA BENTON

Tennessee Gas Pipeline (TGP) · Loc 420948
Power plant delivery · counted in Power Generation
Gas day Nov 27
0.100
Bcf/d scheduled
Δ Day-over-day
+0.000
vs Nov 26
7-day average
0.071
Bcf/d
30-day average
0.051
30 of 30 days posted
30-day high
0.100
Nov 27
30-day low
0.025
Nov 2
Operating capacity
0.184
Bcf/d as posted, evening cycle
Utilization
54%
headroom 46%

Scheduled quantities as posted by Tennessee Gas Pipeline (TGP) on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the Power Generation page.

0.0000.0250.0500.0750.100Oct 29Nov 3Nov 8Nov 13Nov 18Nov 23 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 270.100+0.000
Nov 260.100+0.019
Nov 250.081+0.015
Nov 240.066+0.003
Nov 230.064+0.019
Nov 220.045+0.005
Nov 210.040-0.005
Nov 200.045-0.005
Nov 190.050-0.026
Nov 180.076+0.029
Nov 170.046-0.000
Nov 160.046+0.000
Nov 150.046+0.007
Nov 140.039-0.005
Nov 130.044-0.000
Nov 120.045+0.000
Nov 110.045+0.000
Nov 100.045+0.000
Nov 90.045+0.001
Nov 80.044-0.001
Nov 70.045+0.000
Nov 60.045-0.000
Nov 50.045+0.000
Nov 40.045-0.019
Nov 30.064+0.039
Nov 20.025+0.000
Nov 10.025-0.010
Oct 310.035+0.000
Oct 300.035-0.030
Oct 290.064—
83 more days on file for this meter, back to August 7, 2026. Full meter-level history is part of Institutional (API and downloads).
Tennessee Gas PipelineTVA/TGP MAGNOLIA BENTON

Tennessee Gas PipelinePlant location from EIA Form 860 (plant 55451).

Recent notices on Tennessee Gas Pipeline (TGP)

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Tennessee Gas Pipeline (TGP) notices →

Tennessee Gas Pipeline (TGP) · posted 2026-11-21 · effective 2026-11-16 · informational
Tennessee Gas Pipeline (TGP) · posted 2026-11-16 · effective 2026-11-16 · force majeure
TGP force majeure at Station 542 Unit 2A near De Kalb, MS remains in effect with no restoration timeline. Up to 250,000 Dth/d (0.25 Bcf/d) of Primary firm capacity pathed through Segment 539 BH is at risk of curtailment beginning Timely Cycle for gas day November 17. This Revisio…
Tennessee Gas Pipeline (TGP) · posted 2026-11-05 · effective 2026-11-06 · informational