TVA/TGP JOHNSONVILLE HICKMAN

Tennessee Gas Pipeline (TGP) · Loc 420907
Power plant delivery · counted in Power Generation
Gas day Nov 27
0.137
Bcf/d scheduled
Δ Day-over-day
+0.000
vs Nov 26
7-day average
0.136
Bcf/d
30-day average
0.103
30 of 30 days posted
30-day high
0.168
Nov 22
30-day low
0.044
Nov 1
Operating capacity
0.638
Bcf/d as posted, evening cycle
Utilization
22%
headroom 78%

Scheduled quantities as posted by Tennessee Gas Pipeline (TGP) on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the Power Generation page.

0.000.050.100.150.20Oct 29Nov 3Nov 8Nov 13Nov 18Nov 23 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 270.137+0.000
Nov 260.137+0.010
Nov 250.127+0.012
Nov 240.115+0.016
Nov 230.099-0.069
Nov 220.168+0.000
Nov 210.168+0.000
Nov 200.168+0.043
Nov 190.125+0.023
Nov 180.102+0.001
Nov 170.102-0.016
Nov 160.118+0.015
Nov 150.103+0.000
Nov 140.103+0.033
Nov 130.070-0.014
Nov 120.084-0.024
Nov 110.108+0.025
Nov 100.083-0.001
Nov 90.084+0.000
Nov 80.084+0.000
Nov 70.084-0.019
Nov 60.103+0.003
Nov 50.100-0.003
Nov 40.103+0.015
Nov 30.088+0.024
Nov 20.064+0.020
Nov 10.044-0.020
Oct 310.064+0.000
Oct 300.064-0.019
Oct 290.083—
83 more days on file for this meter, back to August 7, 2026. Full meter-level history is part of Institutional (API and downloads).
Tennessee Gas PipelineTVA/TGP JOHNSONVILLE HICKMAN

Tennessee Gas PipelinePlaced at the center of Hickman, TN — approximate; the exact meter site is not published.

Recent notices on Tennessee Gas Pipeline (TGP)

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Tennessee Gas Pipeline (TGP) notices →

Tennessee Gas Pipeline (TGP) · posted 2026-11-21 · effective 2026-11-16 · informational
Tennessee Gas Pipeline (TGP) · posted 2026-11-16 · effective 2026-11-16 · force majeure
TGP force majeure at Station 542 Unit 2A near De Kalb, MS remains in effect with no restoration timeline. Up to 250,000 Dth/d (0.25 Bcf/d) of Primary firm capacity pathed through Segment 539 BH is at risk of curtailment beginning Timely Cycle for gas day November 17. This Revisio…
Tennessee Gas Pipeline (TGP) · posted 2026-11-05 · effective 2026-11-06 · informational

Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.

Cite thisEnercast PipeScrape, TVA/TGP JOHNSONVILLE HICKMAN (Tennessee Gas Pipeline (TGP) loc 420907) scheduled quantity, gas day November 27, 2026. https://enercast.com/meter/tgp/420907/