Enercast has launched New Storage, its own survey of U.S. underground natural gas storage projects: new salt-cavern and depleted-reservoir fields, new caverns at existing sites, expansions, capacity reductions and field retirements, interstate and intrastate. It covers every project that adds or removes at least 2 Bcf of working gas or 0.1 Bcf/d of withdrawal: 27 projects at launch, each with a named, dated source beside every status, capacity and date.
Find it under Capacity in the top menu, alongside Capacity Offline (today’s outages and maintenance) and New Pipelines, its sibling tracker for pipeline projects. It also has a card on the homepage.

The headline figures
As of November 23, 2026, adding up each project’s stated working gas:
- 164.3 Bcf under construction, 8 projects.
- 85.5 Bcf approved and not yet building, 8 projects with a FERC certificate or, for intrastate projects, a final investment decision.
- 166.3 Bcf proposed, 8 projects announced, in pre-filing or applied, net of one capacity reduction.
- 13.0 Bcf in service in the last 12 months, one project.
These are working gas capacities as each project’s source states them, added up. They are not a forecast of storage capacity or of inventories, and Enercast does not measure any of them.
Almost all of it is on the Gulf Coast. Of the stated working gas in the tracker’s additions, 98% is in Texas, Louisiana and Mississippi, and about 85% is in salt caverns, the fast-cycling kind of storage that can inject and withdraw several times a year. It sits in the same region as the LNG export terminals, whose feedgas demand has grown this year.
Working gas and withdrawal are two different numbers
The headline unit is working gas, in Bcf: how much gas a project adds that can be put in and taken out. Withdrawal, in Bcf/d, is how fast it can come out. The page shows both, side by side, and never adds one to the other. Not every source states both: only 9 of the 25 projects in the tiles state a withdrawal rate.
NGPL’s Gulf Coast Storage Expansion at the North Lansing field in Texas shows why. It turns about 10 Bcf of cushion gas into working gas, and, separately, its application raises the field’s certificated peak-day withdrawal from 1,240 MMcf/d to 1,420 MMcf/d. Both appear on its page, each with its source.
How it is compiled
Unlike pipelines, storage has no public project list to start from. EIA publishes a tracker of pipeline projects, which is one of New Pipelines’ sources, but its storage data covers fields that are already operating. So New Storage is built from filings and from the sponsors themselves. Sources are checked every night:
- FERC. The docket of every open interstate project: applications, certificate and prior-notice orders, construction authorizations and in-service notices. A nightly search of FERC filings and the Federal Register looks for new storage applications.
- State regulators. Intrastate projects in Texas and Louisiana are permitted by the state, not FERC. Their status comes from the state permit and the sponsor, and “Approved” means a final investment decision.
- The sponsors. Project pages, earnings releases and investor presentations. AI reads the page. A finding is kept only if the figure or date appears word for word in a quoted passage, and only a figure the source calls working gas is recorded as working gas. A total, or the facility’s size after the project, is not. A page that would move a project backwards is treated as out of date.
- EIA. EIA’s field-level storage data is a cross-check after a project is operating.
Every change is then checked automatically against its source. The riskier kinds wait for a person at Enercast: a new project, a reduction, a status moving backwards, a large capacity change, or two sources that disagree.
Three projects, three kinds of source
- A sponsor’s own page. Golden Triangle Caverns 3 and 4, a 14 Bcf (stated) cavern expansion in Texas, was listed for “2027”. Caliche’s project page says the caverns are “anticipated to be in-service by the third quarter of 2027”, and on November 18 the page changed to that wording, with the quote beside it.
- FERC. Black Bayou, a four-cavern salt storage project in Louisiana, is under construction after a FERC letter of October 20, 2026. Its working gas is stated at 44.4 Bcf, up from 34.7 Bcf when it was certificated in 2025, after a 2026 amendment raised the working gas per cavern.
- No FERC filing at all. Pickton Gas Storage in Northeast Texas reached a final investment decision in July 2026 on a 35 Bcf (stated) facility, with commercial operations expected “in spring 2028”, as reported at the time. It is intrastate, so it never appears at FERC. That is why sponsors and the trade press are watched as well as the regulators.
Pickton also carries the No regulator filing yet tag, as do three other projects today. It means there is no FERC docket, state permit or regulator document on file for the project yet, so its status rests on the sponsor and press reports.
Reductions and retirements
Storage can shrink as well as grow, and the tracker counts both. A capacity reduction is netted into the totals: East Cheyenne’s application to reduce its working gas by 10 Bcf is subtracted from the Proposed tile. A whole-field retirement is shown separately and not netted: Columbia Gas Transmission has applied to abandon the Majorsville-Heard storage complex in West Virginia and Pennsylvania, 34.8 Bcf stated. A field that is already inactive isn’t formally retired until FERC approves the abandonment, so subtracting it now would make the totals move for a change that has not happened.
Charts, map and project pages
The page opens with those four figures, then a chart of stated working gas by stated in-service year or quarter, stacked by status, with reductions below the axis. A map shows the Texas–Louisiana–Mississippi cluster, and New storage projects is also a layer on the Capacity Offline map. Map locations are approximate, placed by county or parish. Each project has its own page: a one-sentence summary, its facts with a source beside each, milestones, a change log, and the sources with the quoted sentence.
Who gets what
- The website and free subscribers: weekly. The pages are rebuilt on Sunday, and Monday’s free brief lists the week’s changes in the Storage part of “New capacity this week”.
- Pro subscribers: daily, in the Opening brief by email and Telegram, on days something changed, in the Storage part of the New capacity section. These are detected and checked automatically overnight; any held for a person’s check are marked “(held)”. Pro and Institutional subscribers can also download the tracker as CSV files from the data downloads page.
How each source is used, what each status means and how reductions are counted is in How New Storage works. For pipeline projects, see New Pipelines. This article is for education, not investment advice.
Try it on enercast.com
- New Storage — all 27 projects, the chart, the map and this week’s changes
- How New Storage works — statuses, sources, reductions and FAQ
- Storage map — New storage projects as a layer on the Capacity Offline map
- Black Bayou — a project page
- New Pipelines — the sibling tracker for pipeline projects
Sources: FERC eLibrary (dockets CP24-494, CP26-257, CP23-542, CP26-568, CP25-52, CP25-95, CP26-527) · Federal Register, including FR 2025-01868 (NGPL Gulf Coast Storage Expansion, Jan 29, 2025) · EIA, natural gas storage field data · Caliche, GTS Expansion project page (read Nov 18, 2026) · NGI, Black Bayou starts construction (Nov 17, 2026) · P&GJ, Pickton reaches FID (Jul 16, 2026). Not investment advice; see the disclaimer.
More from Pipeline News
- Historically, U.S. gas production's seasonal gain comes before Thanksgiving, not in December · Nov 25, 2026
- U.S. gas supply bounces back to a November record as Appalachia and Haynesville return · Nov 18, 2026
- Which U.S. gas pipelines are actually getting built? A new Enercast tracker, sourced line by line · Nov 15, 2026
- Canada is sending less gas south as LNG Canada ramps up · Nov 12, 2026