Enercast — at the moment it matters
Enercast  /  Pipeline News  /  Enercast Update

Where is new U.S. natural gas storage being built? A new Enercast tracker, sourced line by line

New Storage follows 27 U.S. underground natural gas storage projects, from salt caverns to depleted fields, with a named, dated source beside every status, working gas figure and date.

Enercast Update  ·  Nov 23, 2026

Enercast has launched New Storage, its own survey of U.S. underground natural gas storage projects: new salt-cavern and depleted-reservoir fields, new caverns at existing sites, expansions, capacity reductions and field retirements, interstate and intrastate. It covers every project that adds or removes at least 2 Bcf of working gas or 0.1 Bcf/d of withdrawal: 27 projects at launch, each with a named, dated source beside every status, capacity and date.

Find it under Capacity in the top menu, alongside Capacity Offline (today’s outages and maintenance) and New Pipelines, its sibling tracker for pipeline projects. It also has a card on the homepage.

The New Storage page on enercast.com: headline tiles for working gas under construction, approved, proposed and recently in service
The New Storage page, November 23, 2026.

The headline figures

As of November 23, 2026, adding up each project’s stated working gas:

These are working gas capacities as each project’s source states them, added up. They are not a forecast of storage capacity or of inventories, and Enercast does not measure any of them.

Almost all of it is on the Gulf Coast. Of the stated working gas in the tracker’s additions, 98% is in Texas, Louisiana and Mississippi, and about 85% is in salt caverns, the fast-cycling kind of storage that can inject and withdraw several times a year. It sits in the same region as the LNG export terminals, whose feedgas demand has grown this year.

Working gas and withdrawal are two different numbers

The headline unit is working gas, in Bcf: how much gas a project adds that can be put in and taken out. Withdrawal, in Bcf/d, is how fast it can come out. The page shows both, side by side, and never adds one to the other. Not every source states both: only 9 of the 25 projects in the tiles state a withdrawal rate.

NGPL’s Gulf Coast Storage Expansion at the North Lansing field in Texas shows why. It turns about 10 Bcf of cushion gas into working gas, and, separately, its application raises the field’s certificated peak-day withdrawal from 1,240 MMcf/d to 1,420 MMcf/d. Both appear on its page, each with its source.

How it is compiled

Unlike pipelines, storage has no public project list to start from. EIA publishes a tracker of pipeline projects, which is one of New Pipelines’ sources, but its storage data covers fields that are already operating. So New Storage is built from filings and from the sponsors themselves. Sources are checked every night:

Every change is then checked automatically against its source. The riskier kinds wait for a person at Enercast: a new project, a reduction, a status moving backwards, a large capacity change, or two sources that disagree.

Three projects, three kinds of source

Pickton also carries the No regulator filing yet tag, as do three other projects today. It means there is no FERC docket, state permit or regulator document on file for the project yet, so its status rests on the sponsor and press reports.

Reductions and retirements

Storage can shrink as well as grow, and the tracker counts both. A capacity reduction is netted into the totals: East Cheyenne’s application to reduce its working gas by 10 Bcf is subtracted from the Proposed tile. A whole-field retirement is shown separately and not netted: Columbia Gas Transmission has applied to abandon the Majorsville-Heard storage complex in West Virginia and Pennsylvania, 34.8 Bcf stated. A field that is already inactive isn’t formally retired until FERC approves the abandonment, so subtracting it now would make the totals move for a change that has not happened.

Charts, map and project pages

The page opens with those four figures, then a chart of stated working gas by stated in-service year or quarter, stacked by status, with reductions below the axis. A map shows the Texas–Louisiana–Mississippi cluster, and New storage projects is also a layer on the Capacity Offline map. Map locations are approximate, placed by county or parish. Each project has its own page: a one-sentence summary, its facts with a source beside each, milestones, a change log, and the sources with the quoted sentence.

Who gets what

How each source is used, what each status means and how reductions are counted is in How New Storage works. For pipeline projects, see New Pipelines. This article is for education, not investment advice.

Try it on enercast.com

Sources: FERC eLibrary (dockets CP24-494, CP26-257, CP23-542, CP26-568, CP25-52, CP25-95, CP26-527) · Federal Register, including FR 2025-01868 (NGPL Gulf Coast Storage Expansion, Jan 29, 2025) · EIA, natural gas storage field data · Caliche, GTS Expansion project page (read Nov 18, 2026) · NGI, Black Bayou starts construction (Nov 17, 2026) · P&GJ, Pickton reaches FID (Jul 16, 2026). Not investment advice; see the disclaimer.