Natural Gas Pipeline Company of America LLC (Kinder Morgan) · 10 Bcf working gas stated · Under construction

Gulf Coast Storage Expansion Project (NGPL) is a storage expansion (depleted reservoir) by Natural Gas Pipeline Company of America LLC (Kinder Morgan) in TX. It is under construction. Stated working gas added is 10 Bcf. Stated withdrawal capability added is 0.18 Bcf/d. In-service timing is stated as April 1, 2027. FERC docket CP25-52. Sources: FERC filings, the Federal Register and the sponsor's public material. Last verified by Enercast on Nov 19, 2026.

StatusUnder construction
Working gas10 Bcf stated
10 Bcf firm storage (NSS) capacity; FR describes converting cushion gas to working gas; certificated peak-day withdrawal 1,240 -> 1,420 MMcf/d (+0.18 Bcf/d, the difference of the two stated figures)
Withdrawal0.18 Bcf/d statedFederal Register, dated Jan 29, 2025
InjectionNot stated—
In-service timingApril 1, 2027 stated
OperatorNatural Gas Pipeline Company of America LLC (Kinder Morgan)
Project typeExpansion
Storage typeDepleted reservoir
FacilityNorth Lansing Storage Field, Harrison CountyFederal Register, dated Jan 29, 2025
StatesTX
EIA storage regionSouth Central
JurisdictionInterstate (FERC-regulated) · FERC
FERC docketCP25-52
Last verifiedNov 19, 2026all sources fetched

Facts with no source beside them were compiled by Enercast from the documents listed under Sources when the project was first listed.

Working gas, withdrawal and in-service timing are what the source states. None is measured or forecast by Enercast. How to read this page. Updated weekly.

Milestones

No dated milestones recorded yet. They are added as FERC filings, orders and in-service notices appear.

Change log

No changes since this project was first listed on Nov 17, 2026.

Sources

← All new storage projects