How New Storage Works

Stated working gas and stated dates for storage projects, each traced to its source.

Updated weekly.

What the tracker shows

New Storage lists U.S. underground natural gas storage projects: new salt-cavern and depleted-reservoir fields, new caverns at existing sites, expansions, capacity reductions and field abandonments, interstate (FERC) and intrastate. Each has a status, a stated working gas, a stated withdrawal capability where one is given, the sponsor’s stated in-service timing, dated milestones and a change log. It sits beside New Pipelines, which tracks pipeline projects.

Everything is stated by someone else. Enercast does not estimate how big a storage project is or when it will start. The page reports what FERC, the state regulator, the sponsor or the trade press has said, shows which of them said it, and records each time it changes.

What each status means

StatusMeaning
AnnouncedThe sponsor has named the project. No certificate application and no final investment decision.
Pre-filingIn FERC’s pre-filing process: a docket exists, but no certificate application yet.
AppliedCertificate (or prior-notice) application filed with FERC and not yet decided.
ApprovedFERC certificate issued, or, for an intrastate project that needs none, a final investment decision taken.
Under constructionConstruction, drilling or cavern leaching has started.
Partial serviceSome of the project’s caverns or capacity are in service.
In serviceThe whole project is in service.
On holdThe sponsor has paused or delayed it without a new date.
CancelledThe sponsor has withdrawn it.

Which source is used for what

How it stays current

Every night Enercast re-reads the FERC docket of every open project, searches FERC and the Federal Register for new storage filings, and reads a list of sponsor pages. Anything that changed becomes a proposed update with the passage it came from, and is checked automatically: a figure or date must appear word for word in the quoted passage, a status may not move backwards, a date may not become vaguer, and a figure must be the working gas the project adds, not a total. Changes that pass are recorded the same night; the riskier kinds are held until a person at Enercast has checked them. These pages are rebuilt weekly, on Sunday.

New Storage FAQ

Where do the dates and capacities come from?

From FERC (dockets, orders and Federal Register notices), state regulators, the sponsor (project pages, earnings material, press releases) and trade press, cross-checked against EIA’s field-level storage data (form EIA-191). Every row on a project page links the source behind it.

What is working gas, and why is it the headline?

Working gas is the gas a storage field can inject and withdraw in a cycle, on top of the base (cushion) gas that stays in the ground. It is the figure that matters for how much the market can store, so the tracker adds it up. Where a source gives only total gas capacity, or the facility’s size after the project, the working gas added is shown as not stated and the project is left out of the totals rather than guessed.

Why is withdrawal shown separately?

Withdrawal (deliverability) is a rate, in Bcf per day; working gas is a volume, in Bcf. They cannot be added together. A high-turn salt cavern may add modest working gas but a lot of daily withdrawal.

How are reductions and retirements handled?

A project that lowers a facility’s stated capacity is shown with negative figures and netted into the totals. A whole field a pipeline has applied to abandon is listed under Pending retirements and is not netted: an inactive field is not formally retired until FERC approves the abandonment.

What does “No regulator filing yet” mean?

Enercast has no FERC docket, state permit or regulator document on file for the project. What is shown comes from the sponsor or trade press. Intrastate projects (Texas and Louisiana, mostly) are permitted by the state, not FERC.

How often is this updated?

These pages are updated weekly, on Sunday. The sources are checked every night, and a change appears here only after it has passed automatic checks against its source; the riskier kinds (a new project, a reduction, a status moving backwards, a large capacity change, or two sources that disagree) are held for a manual check first. “Verified” moves forward only when the project’s sources were fetched successfully.

Is the yearly total a forecast?

No. It adds up the working gas sponsors and regulators state, by the year they say the project will enter service. Storage is built cavern by cavern over years, and announced projects may never be built.

Why is a project missing?

The tracker covers U.S. underground storage projects that add or remove at least 2 Bcf of working gas or 0.1 Bcf/d of withdrawal. LNG tanks, peak-shaving plants and smaller projects are left out. If something that qualifies is missing, email [email protected].

More questions? See the general FAQ or email [email protected].