Golden Triangle Caverns 3 and 4 Expansion is a storage cavern addition (salt cavern) by Golden Triangle Storage, LLC (Caliche) in TX. It is under construction. Stated working gas added is 14 Bcf. In-service timing is stated as by the third quarter of 2027. FERC dockets CP23-542, CP26-568. Sources: FERC filings, the Federal Register, the sponsor's public material and trade press. Last verified by Enercast on Nov 19, 2026.
| Status | Under construction | |
|---|---|---|
| Working gas | 14 Bcf stated 14 Bcf certificated 2024 (CP23-542); pending amendment CP26-568 would add 12.1 Bcf (7.3 Cavern 3, 4.8 Cavern 4) and injection 1,925 / withdrawal 1,700 MMcf/d | |
| Withdrawal | Not stated | — |
| Injection | Not stated | — |
| In-service timing | by the third quarter of 2027 company-stated | Company, read Nov 18, 2026 |
| Operator | Golden Triangle Storage, LLC (Caliche) | |
| Project type | Cavern addition | |
| Storage type | Salt cavern | |
| States | TX | |
| EIA storage region | South Central | |
| Jurisdiction | Interstate (FERC-regulated) · FERC | |
| FERC docket | CP23-542, CP26-568 | |
| Last verified | Nov 19, 2026 | all sources fetched |
Facts with no source beside them were compiled by Enercast from the documents listed under Sources when the project was first listed.
Working gas, withdrawal and in-service timing are what the source states. None is measured or forecast by Enercast. How to read this page. Updated weekly.
Milestones
No dated milestones recorded yet. They are added as FERC filings, orders and in-service notices appear.
Change log
| Recorded | Field | Change | Source |
|---|---|---|---|
| Nov 18, 2026 | Stated in-service | 2027 → by the third quarter of 2027 | Company, read Nov 18, 2026 |
“Recorded” is the day Enercast recorded the change, not the day it happened.
Sources
- FERC, Jul 23, 2024: FERC eLibrary CP23-542 (order 2024-07-23; construction 2024-10-01)
- Trade press, Jun 4, 2026: P&GJ 2026-06-04
- Federal Register: FR 2026-18360
- Trade press: BIC
- Company: Caliche: GTS Expansion (caverns 3 and 4) project page“Construction of the facilities began October 2024 and is anticipated to be in-service by the third quarter of 2027.”