Enercast — at the moment it matters
Home / Daily Summary / Supply / Production / Meter

BLCKHILL/TGP PORT ROYAL REC BRADFOR

Tennessee Gas Pipeline (TGP) · Loc 57162 · Pennsylvania
Gathering receipt · counted in Supply / Production
Gas day Nov 26
0.116
Bcf/d scheduled
Δ Day-over-day
+0.002
vs Nov 25
7-day average
0.114
Bcf/d
30-day average
0.114
30 of 30 days posted
30-day high
0.124
Oct 31
30-day low
0.106
Nov 13
Operating capacity
0.307
Bcf/d as posted, evening cycle
Utilization
38%
headroom 62%

Scheduled quantities as posted by Tennessee Gas Pipeline (TGP) on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the Supply / Production page.

0.000.050.100.15Oct 28Nov 2Nov 7Nov 12Nov 17Nov 22 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 260.116+0.002
Nov 250.114-0.003
Nov 240.117+0.005
Nov 230.113+0.000
Nov 220.113+0.000
Nov 210.113-0.004
Nov 200.116+0.004
Nov 190.112+0.000
Nov 180.112+0.002
Nov 170.111+0.004
Nov 160.106+0.000
Nov 150.106+0.000
Nov 140.106+0.001
Nov 130.106-0.003
Nov 120.109-0.008
Nov 110.117+0.006
Nov 100.111-0.006
Nov 90.117+0.000
Nov 80.117+0.000
Nov 70.117+0.000
Nov 60.117+0.007
Nov 50.110-0.004
Nov 40.114+0.003
Nov 30.111-0.010
Nov 20.121+0.000
Nov 10.121-0.003
Oct 310.124+0.000
Oct 300.124+0.000
Oct 290.124+0.002
Oct 280.122—
82 more days on file for this meter, back to August 7, 2026. Full meter-level history is part of Institutional (API and downloads).
Tennessee Gas Pipeline

Tennessee Gas PipelineState only (Pennsylvania) — the meter's exact site is not geocoded; the ring marks the state, not the point.

Recent notices on Tennessee Gas Pipeline (TGP)

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Tennessee Gas Pipeline (TGP) notices →

Tennessee Gas Pipeline (TGP) · posted 2026-11-21 · effective 2026-11-16 · informational
Tennessee Gas Pipeline (TGP) · posted 2026-11-16 · effective 2026-11-16 · force majeure
TGP force majeure at Station 542 Unit 2A near De Kalb, MS remains in effect with no restoration timeline. Up to 250,000 Dth/d (0.25 Bcf/d) of Primary firm capacity pathed through Segment 539 BH is at risk of curtailment beginning Timely Cycle for gas day November 17. This Revisio…
Tennessee Gas Pipeline (TGP) · posted 2026-11-05 · effective 2026-11-06 · informational

Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.

Cite thisEnercast PipeScrape, BLCKHILL/TGP PORT ROYAL REC BRADFOR (Tennessee Gas Pipeline (TGP) loc 57162) scheduled quantity, gas day November 26, 2026. https://enercast.com/meter/tgp/57162/