Enercast — at the moment it matters
Home / Daily Summary / Supply / Production / Meter

NFGMIDCL/TGP CLERMONT #2 MC KEAN

Tennessee Gas Pipeline (TGP) · Loc 47743 · Pennsylvania
Gathering receipt · counted in Supply / Production
Gas day Nov 26
0.280
Bcf/d scheduled
Δ Day-over-day
+0.020
vs Nov 25
7-day average
0.262
Bcf/d
30-day average
0.256
30 of 30 days posted
30-day high
0.291
Nov 12
30-day low
0.228
Nov 16
Operating capacity
0.635
Bcf/d as posted, evening cycle
Utilization
44%
headroom 56%

Scheduled quantities as posted by Tennessee Gas Pipeline (TGP) on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the Supply / Production page.

0.000.100.200.30Oct 28Nov 2Nov 7Nov 12Nov 17Nov 22 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 260.280+0.020
Nov 250.260+0.005
Nov 240.255+0.000
Nov 230.255+0.000
Nov 220.255+0.000
Nov 210.255-0.022
Nov 200.277+0.004
Nov 190.273+0.000
Nov 180.273+0.000
Nov 170.273+0.045
Nov 160.228+0.000
Nov 150.228+0.000
Nov 140.228-0.060
Nov 130.288-0.002
Nov 120.291+0.035
Nov 110.255+0.000
Nov 100.255+0.000
Nov 90.255+0.000
Nov 80.255+0.000
Nov 70.255+0.000
Nov 60.255+0.000
Nov 50.255+0.000
Nov 40.255+0.000
Nov 30.255+0.000
Nov 20.255+0.000
Nov 10.255+0.016
Oct 310.240+0.000
Oct 300.240-0.000
Oct 290.240-0.001
Oct 280.240—
82 more days on file for this meter, back to August 7, 2026. Full meter-level history is part of Institutional (API and downloads).
Tennessee Gas Pipeline

Tennessee Gas PipelineState only (Pennsylvania) — the meter's exact site is not geocoded; the ring marks the state, not the point.

Recent notices on Tennessee Gas Pipeline (TGP)

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Tennessee Gas Pipeline (TGP) notices →

Tennessee Gas Pipeline (TGP) · posted 2026-11-21 · effective 2026-11-16 · informational
Tennessee Gas Pipeline (TGP) · posted 2026-11-16 · effective 2026-11-16 · force majeure
TGP force majeure at Station 542 Unit 2A near De Kalb, MS remains in effect with no restoration timeline. Up to 250,000 Dth/d (0.25 Bcf/d) of Primary firm capacity pathed through Segment 539 BH is at risk of curtailment beginning Timely Cycle for gas day November 17. This Revisio…
Tennessee Gas Pipeline (TGP) · posted 2026-11-05 · effective 2026-11-06 · informational

Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.

Cite thisEnercast PipeScrape, NFGMIDCL/TGP CLERMONT #2 MC KEAN (Tennessee Gas Pipeline (TGP) loc 47743) scheduled quantity, gas day November 26, 2026. https://enercast.com/meter/tgp/47743/