Enercast — at the moment it matters
Home / Daily Summary / Supply / Production / Meter

ETC NEPL/TGP ALLEN MEADOW DEHY:RIP

Tennessee Gas Pipeline (TGP) · Loc 412784 · Pennsylvania
Processing plant · counted in Supply / Production
Gas day Nov 26
0.040
Bcf/d scheduled
Δ Day-over-day
-0.000
vs Nov 25
7-day average
0.040
Bcf/d
30-day average
0.024
30 of 30 days posted
30-day high
0.040
Nov 25
30-day low
0.006
Nov 13
Operating capacity
0.089
Bcf/d as posted, evening cycle
Utilization
45%
headroom 55%

Scheduled quantities as posted by Tennessee Gas Pipeline (TGP) on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the Supply / Production page.

0.0000.0200.0400.060Oct 28Nov 2Nov 7Nov 12Nov 17Nov 22 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 260.040-0.000
Nov 250.040+0.000
Nov 240.040+0.000
Nov 230.040+0.000
Nov 220.040+0.000
Nov 210.040+0.000
Nov 200.040+0.004
Nov 190.036+0.000
Nov 180.036+0.000
Nov 170.036-0.000
Nov 160.037+0.000
Nov 150.037+0.000
Nov 140.037+0.031
Nov 130.006-0.001
Nov 120.007+0.000
Nov 110.007+0.000
Nov 100.007-0.000
Nov 90.007+0.000
Nov 80.007+0.000
Nov 70.007+0.000
Nov 60.007+0.000
Nov 50.007-0.000
Nov 40.007+0.000
Nov 30.007+0.000
Nov 20.007+0.000
Nov 10.007-0.021
Oct 310.028+0.000
Oct 300.028-0.001
Oct 290.029-0.009
Oct 280.038—
82 more days on file for this meter, back to August 7, 2026. Full meter-level history is part of Institutional (API and downloads).
Tennessee Gas Pipeline

Tennessee Gas PipelineState only (Pennsylvania) — the meter's exact site is not geocoded; the ring marks the state, not the point.

Recent notices on Tennessee Gas Pipeline (TGP)

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Tennessee Gas Pipeline (TGP) notices →

Tennessee Gas Pipeline (TGP) · posted 2026-11-21 · effective 2026-11-16 · informational
Tennessee Gas Pipeline (TGP) · posted 2026-11-16 · effective 2026-11-16 · force majeure
TGP force majeure at Station 542 Unit 2A near De Kalb, MS remains in effect with no restoration timeline. Up to 250,000 Dth/d (0.25 Bcf/d) of Primary firm capacity pathed through Segment 539 BH is at risk of curtailment beginning Timely Cycle for gas day November 17. This Revisio…
Tennessee Gas Pipeline (TGP) · posted 2026-11-05 · effective 2026-11-06 · informational

Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.

Cite thisEnercast PipeScrape, ETC NEPL/TGP ALLEN MEADOW DEHY:RIP (Tennessee Gas Pipeline (TGP) loc 412784) scheduled quantity, gas day November 26, 2026. https://enercast.com/meter/tgp/412784/