Enercast — at the moment it matters
Home / Daily Summary / Power Generation / Meter

AECI Plant Sto - Essex Pwr Plt -Stoddard Co, MO

Texas Eastern Transmission (TETCO) · Loc 73207
Power plant delivery · counted in Power Generation
Gas day Nov 27
0.000
Bcf/d scheduled
Δ Day-over-day
+0.000
vs Nov 26
7-day average
0.005
Bcf/d
30-day average
0.003
30 of 30 days posted
30-day high
0.018
Nov 24
30-day low
0.000
Nov 27
Operating capacity
0.073
Bcf/d as posted, late_0005 cycle
Utilization
0%
headroom 100%

Scheduled quantities as posted by Texas Eastern Transmission (TETCO) on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the Power Generation page.

0.0000.0050.0100.0150.020Oct 29Nov 3Nov 8Nov 13Nov 18Nov 23 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 270.000+0.000
Nov 260.000-0.006
Nov 250.006-0.011
Nov 240.018+0.014
Nov 230.004+0.000
Nov 220.004+0.000
Nov 210.004+0.000
Nov 200.004-0.012
Nov 190.016+0.012
Nov 180.004+0.004
Nov 170.000+0.000
Nov 160.000+0.000
Nov 150.000+0.000
Nov 140.000-0.006
Nov 130.006+0.006
Nov 120.000+0.000
Nov 110.000+0.000
Nov 100.000+0.000
Nov 90.000+0.000
Nov 80.000+0.000
Nov 70.000-0.005
Nov 60.005+0.005
Nov 50.000+0.000
Nov 40.000+0.000
Nov 30.000-0.012
Nov 20.012+0.002
Nov 10.010+0.010
Oct 310.000-0.005
Oct 300.005+0.005
Oct 290.000—
79 more days on file for this meter, back to August 11, 2026. Full meter-level history is part of Institutional (API and downloads).
Texas Eastern (TETCO)AECI Plant Sto - Essex Pwr Plt -Stoddard Co, MO

Texas Eastern (TETCO)Plant location from EIA Form 860 (plant 7749).

Recent notices on Texas Eastern Transmission (TETCO)

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Texas Eastern Transmission (TETCO) notices →

Texas Eastern Transmission (TETCO) · posted 2026-11-25 · effective 2026-11-26 · informational
Texas Eastern Transmission (TETCO) · posted 2026-11-12 · effective 2026-11-12 · informational
Texas Eastern Transmission (TETCO) · posted 2026-11-05 · effective 2026-11-07 · informational
Texas Eastern Transmission (TETCO) · posted 2026-10-30 · effective 2026-09-25 · informational
Texas Eastern Transmission (TETCO) · posted 2026-10-30 · effective 2026-10-02 · informational
Texas Eastern Transmission (TETCO) · posted 2026-10-30 · effective 2026-10-02 · capacity constraint
TETCO has declared an unplanned outage between Tompkinsville and Danville Compressor Stations on Line 15 Valve Sections 2-4, requiring an immediate pressure restriction effective Gas Day October 6, 2026. North-to-South capacity on the 30-inch system is reduced to a minimum of app…
Texas Eastern Transmission (TETCO) · posted 2026-10-30 · effective 2026-10-02 · force majeure
TETCO has declared a Force Majeure due to an unplanned outage on its 30-inch system north of Tompkinsville Compressor Station in Kentucky, affecting Line 15 Valve Sections 2-4 and also implicating Danville Compressor Station. The restoration timeline is unknown ('unclear at this …
Texas Eastern Transmission (TETCO) · posted 2026-10-30 · effective 2026-10-07 · capacity constraint
TETCO is providing an update on the unplanned outage on Line 15 between the Tompkinsville and Danville compressor stations (Valve Sections 2-4), originally posted under Notice 183681. Primary Firm nomination restrictions remain in effect with no fixed end date; TETCO targets a re…

Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.

Cite thisEnercast PipeScrape, AECI Plant Sto - Essex Pwr Plt -Stoddard Co, MO (Texas Eastern Transmission (TETCO) loc 73207) scheduled quantity, gas day November 27, 2026. https://enercast.com/meter/tetco/73207/