Enercast — at the moment it matters
Home / Daily Summary / LDC Citygate / Meter

BOSTN/TGP 268 CDP - BOSTON GAS

Tennessee Gas Pipeline (TGP) · Loc 47861 · MIDDLESEX, Massachusetts
LDC citygate delivery · counted in LDC Citygate
Gas day Nov 26
0.104
Bcf/d scheduled
Δ Day-over-day
-0.064
vs Nov 25
7-day average
0.125
Bcf/d
30-day average
0.117
30 of 30 days posted
30-day high
0.188
Nov 13
30-day low
0.057
Oct 30
Operating capacity
0.363
Bcf/d as posted, evening cycle
Utilization
29%
headroom 71%

Scheduled quantities as posted by Tennessee Gas Pipeline (TGP) on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the LDC Citygate page.

0.000.050.100.150.20Oct 28Nov 2Nov 7Nov 12Nov 17Nov 22 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 260.104-0.064
Nov 250.167-0.000
Nov 240.167+0.057
Nov 230.110+0.003
Nov 220.107+0.002
Nov 210.105-0.009
Nov 200.114-0.002
Nov 190.117+0.000
Nov 180.117-0.016
Nov 170.133-0.026
Nov 160.159-0.001
Nov 150.160-0.003
Nov 140.163-0.025
Nov 130.188+0.076
Nov 120.113+0.000
Nov 110.112-0.003
Nov 100.116+0.001
Nov 90.115+0.010
Nov 80.105+0.001
Nov 70.104+0.017
Nov 60.086-0.001
Nov 50.087+0.003
Nov 40.085-0.016
Nov 30.101-0.008
Nov 20.109-0.024
Nov 10.133+0.034
Oct 310.099+0.042
Oct 300.057-0.012
Oct 290.069-0.033
Oct 280.102—
82 more days on file for this meter, back to August 7, 2026. Full meter-level history is part of Institutional (API and downloads).
Tennessee Gas PipelineBOSTN/TGP 268 CDP - BOSTON GAS

Tennessee Gas PipelinePlaced at the center of Middlesex, MA — approximate; the exact meter site is not published.

Recent notices on Tennessee Gas Pipeline (TGP)

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Tennessee Gas Pipeline (TGP) notices →

Tennessee Gas Pipeline (TGP) · posted 2026-11-21 · effective 2026-11-16 · informational
Tennessee Gas Pipeline (TGP) · posted 2026-11-16 · effective 2026-11-16 · force majeure
TGP force majeure at Station 542 Unit 2A near De Kalb, MS remains in effect with no restoration timeline. Up to 250,000 Dth/d (0.25 Bcf/d) of Primary firm capacity pathed through Segment 539 BH is at risk of curtailment beginning Timely Cycle for gas day November 17. This Revisio…
Tennessee Gas Pipeline (TGP) · posted 2026-11-05 · effective 2026-11-06 · informational

Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.

Cite thisEnercast PipeScrape, BOSTN/TGP 268 CDP - BOSTON GAS (Tennessee Gas Pipeline (TGP) loc 47861) scheduled quantity, gas day November 26, 2026. https://enercast.com/meter/tgp/47861/