Gas day Nov 26
0.057
Bcf/d scheduled
Δ Day-over-day
+0.007
vs Nov 25
7-day average
0.048
Bcf/d
30-day average
0.043
30 of 30 days posted
30-day high
0.067
Oct 31
30-day low
0.022
Nov 7
Operating capacity
0.054
Bcf/d as posted, evening cycle
Utilization
107%
scheduled above operating capacity

Scheduled quantities as posted by Tennessee Gas Pipeline (TGP) on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the LDC Citygate page.

0.0000.0200.0400.0600.080Oct 28Nov 2Nov 7Nov 12Nov 17Nov 22 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 260.057+0.007
Nov 250.050-0.001
Nov 240.051+0.001
Nov 230.050+0.018
Nov 220.033-0.015
Nov 210.048+0.004
Nov 200.043+0.004
Nov 190.040-0.001
Nov 180.040-0.025
Nov 170.065+0.003
Nov 160.062+0.003
Nov 150.060-0.001
Nov 140.061+0.033
Nov 130.028-0.015
Nov 120.042+0.001
Nov 110.042+0.006
Nov 100.035-0.010
Nov 90.045+0.002
Nov 80.043+0.021
Nov 70.022-0.005
Nov 60.027+0.002
Nov 50.025-0.001
Nov 40.026+0.001
Nov 30.025+0.002
Nov 20.024-0.035
Nov 10.058-0.009
Oct 310.067+0.027
Oct 300.040+0.010
Oct 290.030-0.019
Oct 280.049—
82 more days on file for this meter, back to August 7, 2026. Full meter-level history is part of Institutional (API and downloads).
Tennessee Gas PipelineBOSTN/TGP 261 CDP - BOSTON

Tennessee Gas PipelinePlaced at the center of Hampden, MA — approximate; the exact meter site is not published.

Recent notices on Tennessee Gas Pipeline (TGP)

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Tennessee Gas Pipeline (TGP) notices →

Tennessee Gas Pipeline (TGP) · posted 2026-11-21 · effective 2026-11-16 · informational
Tennessee Gas Pipeline (TGP) · posted 2026-11-16 · effective 2026-11-16 · force majeure
TGP force majeure at Station 542 Unit 2A near De Kalb, MS remains in effect with no restoration timeline. Up to 250,000 Dth/d (0.25 Bcf/d) of Primary firm capacity pathed through Segment 539 BH is at risk of curtailment beginning Timely Cycle for gas day November 17. This Revisio…
Tennessee Gas Pipeline (TGP) · posted 2026-11-05 · effective 2026-11-06 · informational

Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.

Cite thisEnercast PipeScrape, BOSTN/TGP 261 CDP - BOSTON (Tennessee Gas Pipeline (TGP) loc 47859) scheduled quantity, gas day November 26, 2026. https://enercast.com/meter/tgp/47859/