Enercast — at the moment it matters
Home / Daily Summary / LDC Citygate / Meter

BERKSHR/TGP GREENFIELD MA HAMPSHIRE

Tennessee Gas Pipeline (TGP) · Loc 420292 · HAMPSHIRE, Massachusetts
LDC citygate delivery · counted in LDC Citygate
Gas day Nov 26
0.011
Bcf/d scheduled
Δ Day-over-day
+0.000
vs Nov 25
7-day average
0.011
Bcf/d
30-day average
0.011
30 of 30 days posted
30-day high
0.011
Nov 16
30-day low
0.009
Oct 31
Operating capacity
0.012
Bcf/d as posted, evening cycle
Utilization
87%
headroom 13%

Scheduled quantities as posted by Tennessee Gas Pipeline (TGP) on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the LDC Citygate page.

0.0000.0050.0100.015Oct 28Nov 2Nov 7Nov 12Nov 17Nov 22 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 260.011+0.000
Nov 250.011+0.000
Nov 240.011+0.000
Nov 230.011+0.000
Nov 220.011+0.000
Nov 210.011+0.000
Nov 200.011+0.000
Nov 190.011+0.000
Nov 180.011+0.000
Nov 170.011-0.000
Nov 160.011+0.000
Nov 150.011+0.000
Nov 140.011+0.000
Nov 130.011+0.000
Nov 120.011+0.000
Nov 110.011+0.000
Nov 100.011+0.000
Nov 90.011+0.000
Nov 80.011+0.000
Nov 70.011+0.000
Nov 60.011+0.000
Nov 50.011+0.000
Nov 40.011+0.000
Nov 30.011+0.000
Nov 20.011+0.000
Nov 10.011+0.002
Oct 310.009+0.000
Oct 300.009+0.000
Oct 290.009+0.000
Oct 280.009—
82 more days on file for this meter, back to August 7, 2026. Full meter-level history is part of Institutional (API and downloads).
Tennessee Gas PipelineBERKSHR/TGP GREENFIELD MA HAMPSHIRE

Tennessee Gas PipelinePlaced at the center of Hampshire, MA — approximate; the exact meter site is not published.

Recent notices on Tennessee Gas Pipeline (TGP)

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Tennessee Gas Pipeline (TGP) notices →

Tennessee Gas Pipeline (TGP) · posted 2026-11-21 · effective 2026-11-16 · informational
Tennessee Gas Pipeline (TGP) · posted 2026-11-16 · effective 2026-11-16 · force majeure
TGP force majeure at Station 542 Unit 2A near De Kalb, MS remains in effect with no restoration timeline. Up to 250,000 Dth/d (0.25 Bcf/d) of Primary firm capacity pathed through Segment 539 BH is at risk of curtailment beginning Timely Cycle for gas day November 17. This Revisio…
Tennessee Gas Pipeline (TGP) · posted 2026-11-05 · effective 2026-11-06 · informational

Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.

Cite thisEnercast PipeScrape, BERKSHR/TGP GREENFIELD MA HAMPSHIRE (Tennessee Gas Pipeline (TGP) loc 420292) scheduled quantity, gas day November 26, 2026. https://enercast.com/meter/tgp/420292/