Enercast — at the moment it matters
Home / Daily Summary / LDC Citygate / Meter

WPNG ZONE 8

Northwest Pipeline · Loc 222152 · DOUGLAS, Oregon
LDC citygate delivery · counted in LDC Citygate
Gas day Nov 26
0.008
Bcf/d scheduled
Δ Day-over-day
+0.001
vs Nov 25
7-day average
0.010
Bcf/d
30-day average
0.009
30 of 30 days posted
30-day high
0.016
Nov 3
30-day low
0.004
Nov 12

Scheduled quantities as posted by Northwest Pipeline on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the LDC Citygate page.

0.0000.0050.0100.0150.020Oct 28Nov 2Nov 7Nov 12Nov 17Nov 22 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 260.008+0.001
Nov 250.007-0.002
Nov 240.009-0.002
Nov 230.011+0.000
Nov 220.011+0.000
Nov 210.011+0.000
Nov 200.011+0.000
Nov 190.011-0.001
Nov 180.012+0.000
Nov 170.012+0.007
Nov 160.005+0.000
Nov 150.005+0.000
Nov 140.005+0.001
Nov 130.004+0.000
Nov 120.004+0.000
Nov 110.004-0.003
Nov 100.006-0.002
Nov 90.009+0.000
Nov 80.009-0.004
Nov 70.012+0.006
Nov 60.006+0.001
Nov 50.005-0.004
Nov 40.009-0.008
Nov 30.016+0.006
Nov 20.010-0.000
Nov 10.011-0.003
Oct 310.014+0.002
Oct 300.012+0.000
Oct 290.012+0.000
Oct 280.012—
82 more days on file for this meter, back to August 7, 2026. Full meter-level history is part of Institutional (API and downloads).
Northwest PipelineWPNG ZONE 8

Northwest PipelinePlaced at the center of Douglas, OR — approximate; the exact meter site is not published.

Recent notices on Northwest Pipeline

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Northwest Pipeline notices →

Northwest Pipeline · posted 2026-11-03 · operational alert
Northwest Pipeline has issued an OFO Recall Advisory and Operational Flow Order (OFO) effective Gas Day November 4, 2026 and until further notice, through the Roosevelt compressor station. Northbound scheduled quantities are currently exceeding design capacity of 0.546 Bcf/d (0.6…

Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.

Cite thisEnercast PipeScrape, WPNG ZONE 8 (Northwest Pipeline loc 222152) scheduled quantity, gas day November 26, 2026. https://enercast.com/meter/northwest/222152/