Enercast — at the moment it matters
Home / Daily Summary / LDC Citygate / Meter

MOLALLA

Northwest Pipeline · Loc 18398 · CLACKAMAS, Oregon
LDC citygate delivery · counted in LDC Citygate
Gas day Nov 26
0.117
Bcf/d scheduled
Δ Day-over-day
+0.039
vs Nov 25
7-day average
0.051
Bcf/d
30-day average
0.078
30 of 30 days posted
30-day high
0.170
Nov 8
30-day low
0.027
Nov 23
Operating capacity
0.272
Bcf/d as posted, evening cycle
Utilization
43%
headroom 57%

Scheduled quantities as posted by Northwest Pipeline on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the LDC Citygate page.

0.000.050.100.150.20Oct 28Nov 2Nov 7Nov 12Nov 17Nov 22 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 260.117+0.039
Nov 250.078+0.039
Nov 240.039+0.012
Nov 230.027+0.000
Nov 220.027+0.000
Nov 210.027-0.020
Nov 200.047-0.020
Nov 190.067+0.019
Nov 180.048+0.004
Nov 170.044-0.011
Nov 160.054+0.000
Nov 150.054+0.000
Nov 140.054-0.025
Nov 130.080-0.008
Nov 120.088+0.018
Nov 110.070-0.055
Nov 100.125-0.015
Nov 90.140-0.030
Nov 80.170+0.005
Nov 70.165+0.034
Nov 60.131+0.012
Nov 50.119-0.013
Nov 40.132+0.060
Nov 30.073-0.013
Nov 20.085+0.003
Nov 10.083+0.027
Oct 310.056+0.009
Oct 300.047+0.003
Oct 290.044+0.005
Oct 280.038—
82 more days on file for this meter, back to August 7, 2026. Full meter-level history is part of Institutional (API and downloads).
Northwest PipelineMOLALLA

Northwest PipelinePlaced at the center of Clackamas, OR — approximate; the exact meter site is not published.

Recent notices on Northwest Pipeline

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Northwest Pipeline notices →

Northwest Pipeline · posted 2026-11-03 · operational alert
Northwest Pipeline has issued an OFO Recall Advisory and Operational Flow Order (OFO) effective Gas Day November 4, 2026 and until further notice, through the Roosevelt compressor station. Northbound scheduled quantities are currently exceeding design capacity of 0.546 Bcf/d (0.6…

Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.