Enercast — at the moment it matters
Home / Daily Summary / Storage / Meter

Bistineau Injection Expansion

Gulf South Pipeline · Loc 22806 · Gulf Coast
Storage injection / withdrawal · counted in Storage
Gas day Nov 27
-0.091
Bcf/d scheduled
Δ Day-over-day
+0.006
vs Nov 26
7-day average
-0.081
Bcf/d
30-day average
-0.088
30 of 30 days posted
30-day high
-0.059
Nov 12
30-day low
-0.113
Nov 1
Operating capacity
0.260
Bcf/d as posted, eve cycle
Utilization
35%
headroom 65%

Scheduled quantities as posted by Gulf South Pipeline on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Positive = net injection, negative = net withdrawal. Same figure as this meter’s row on the Storage page.

-0.15-0.10-0.05-0.00Oct 29Nov 3Nov 8Nov 13Nov 18Nov 23 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 27-0.091+0.006
Nov 26-0.097-0.027
Nov 25-0.070-0.003
Nov 24-0.067+0.005
Nov 23-0.071+0.014
Nov 22-0.085+0.003
Nov 21-0.088-0.014
Nov 20-0.074+0.009
Nov 19-0.083+0.023
Nov 18-0.106-0.023
Nov 17-0.083+0.016
Nov 16-0.099+0.001
Nov 15-0.100-0.018
Nov 14-0.082+0.008
Nov 13-0.090-0.031
Nov 12-0.059+0.011
Nov 11-0.070+0.025
Nov 10-0.095+0.010
Nov 9-0.105-0.001
Nov 8-0.104+0.005
Nov 7-0.109-0.008
Nov 6-0.102-0.026
Nov 5-0.076+0.014
Nov 4-0.090-0.030
Nov 3-0.059+0.030
Nov 2-0.090+0.023
Nov 1-0.113-0.006
Oct 31-0.107-0.017
Oct 30-0.090-0.012
Oct 29-0.078—
83 more days on file for this meter, back to August 7, 2026. Full meter-level history is part of Institutional (API and downloads).
Gulf South Pipeline

Gulf South PipelineExact site not geocoded — the highlighted line is the pipeline system this meter sits on.

Recent notices on Gulf South Pipeline

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Gulf South Pipeline notices →

Gulf South Pipeline · posted 2026-11-19 · effective 2026-11-20 · informational
Gulf South Pipeline · posted 2026-11-06 · effective 2026-11-06 · informational

Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.

Cite thisEnercast PipeScrape, Bistineau Injection Expansion (Gulf South Pipeline loc 22806) scheduled quantity, gas day November 27, 2026. https://enercast.com/meter/gulfsouth/22806/