EASTERN GAS - OAKFORD, PA-(D70082/R76082) (withdrawal, Texas Eastern Transmission (TETCO))

Texas Eastern Transmission (TETCO) · Loc 75082 · Appalachia
Storage injection / withdrawal · counted in Storage (also Storage)
Gas day Nov 27
-0.132
Bcf/d scheduled
Δ Day-over-day
+0.202
vs Nov 26
7-day average
-0.171
Bcf/d
30-day average
-0.128
30 of 30 days posted
30-day high
-0.000
Nov 5
30-day low
-0.334
Nov 26
Operating capacity
1.428
Bcf/d as posted, late_0005 cycle
Utilization
9%
headroom 91%

Scheduled quantities as posted by Texas Eastern Transmission (TETCO) on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Positive = net injection, negative = net withdrawal. Same figure as this meter’s row on the Storage page.

-0.40-0.30-0.20-0.10-0.00Oct 29Nov 3Nov 8Nov 13Nov 18Nov 23 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 27-0.132+0.202
Nov 26-0.334-0.027
Nov 25-0.307-0.027
Nov 24-0.280-0.182
Nov 23-0.097-0.073
Nov 22-0.025-0.005
Nov 21-0.020+0.043
Nov 20-0.063+0.151
Nov 19-0.213-0.139
Nov 18-0.074+0.134
Nov 17-0.208+0.014
Nov 16-0.222+0.007
Nov 15-0.229-0.111
Nov 14-0.118+0.155
Nov 13-0.273-0.129
Nov 12-0.144-0.099
Nov 11-0.044+0.025
Nov 10-0.069-0.009
Nov 9-0.060+0.009
Nov 8-0.069-0.025
Nov 7-0.044-0.033
Nov 6-0.012-0.012
Nov 5-0.000+0.035
Nov 4-0.035+0.138
Nov 3-0.173+0.076
Nov 2-0.249-0.034
Nov 1-0.215-0.145
Oct 31-0.070-0.019
Oct 30-0.051-0.051
Oct 29-0.000—
79 more days on file for this meter, back to August 11, 2026. Full meter-level history is part of Institutional (API and downloads).
Texas Eastern (TETCO)

Texas Eastern (TETCO)Exact site not geocoded — the highlighted line is the pipeline system this meter sits on.

Recent notices on Texas Eastern Transmission (TETCO)

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Texas Eastern Transmission (TETCO) notices →

Texas Eastern Transmission (TETCO) · posted 2026-11-25 · effective 2026-11-26 · informational
Texas Eastern Transmission (TETCO) · posted 2026-11-12 · effective 2026-11-12 · informational
Texas Eastern Transmission (TETCO) · posted 2026-11-05 · effective 2026-11-07 · informational
Texas Eastern Transmission (TETCO) · posted 2026-10-30 · effective 2026-09-25 · informational
Texas Eastern Transmission (TETCO) · posted 2026-10-30 · effective 2026-10-02 · informational
Texas Eastern Transmission (TETCO) · posted 2026-10-30 · effective 2026-10-02 · capacity constraint
TETCO has declared an unplanned outage between Tompkinsville and Danville Compressor Stations on Line 15 Valve Sections 2-4, requiring an immediate pressure restriction effective Gas Day October 6, 2026. North-to-South capacity on the 30-inch system is reduced to a minimum of app…
Texas Eastern Transmission (TETCO) · posted 2026-10-30 · effective 2026-10-02 · force majeure
TETCO has declared a Force Majeure due to an unplanned outage on its 30-inch system north of Tompkinsville Compressor Station in Kentucky, affecting Line 15 Valve Sections 2-4 and also implicating Danville Compressor Station. The restoration timeline is unknown ('unclear at this …
Texas Eastern Transmission (TETCO) · posted 2026-10-30 · effective 2026-10-07 · capacity constraint
TETCO is providing an update on the unplanned outage on Line 15 between the Tompkinsville and Danville compressor stations (Valve Sections 2-4), originally posted under Notice 183681. Primary Firm nomination restrictions remain in effect with no fixed end date; TETCO targets a re…

Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.

Cite thisEnercast PipeScrape, EASTERN GAS - OAKFORD, PA-(D70082/R76082) (withdrawal, Texas Eastern Transmission (TETCO)) (Texas Eastern Transmission (TETCO) loc 75082) scheduled quantity, gas day November 27, 2026. https://enercast.com/meter/tetco/75082/