Enercast — at the moment it matters
Home / Daily Summary / LDC Citygate / Meter

CGV 01-34

Columbia Gas Transmission (TCO) · Loc 30CS-34 · AUGUSTA, Virginia
LDC citygate delivery · counted in LDC Citygate
Gas day Nov 26
0.028
Bcf/d scheduled
Δ Day-over-day
+0.001
vs Nov 25
7-day average
0.028
Bcf/d
30-day average
0.025
30 of 30 days posted
30-day high
0.033
Nov 6
30-day low
0.010
Oct 31
Operating capacity
0.177
Bcf/d as posted, timely cycle
Utilization
16%
headroom 84%

Scheduled quantities as posted by Columbia Gas Transmission (TCO) on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the LDC Citygate page.

0.0000.0100.0200.0300.040Oct 28Nov 2Nov 7Nov 12Nov 17Nov 22 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 260.028+0.001
Nov 250.028+0.006
Nov 240.021-0.008
Nov 230.029+0.000
Nov 220.029-0.000
Nov 210.029-0.001
Nov 200.030+0.007
Nov 190.023-0.002
Nov 180.025+0.001
Nov 170.024+0.006
Nov 160.018-0.002
Nov 150.020-0.000
Nov 140.021-0.012
Nov 130.032+0.003
Nov 120.029+0.000
Nov 110.029-0.002
Nov 100.031+0.000
Nov 90.031+0.000
Nov 80.030-0.000
Nov 70.030-0.002
Nov 60.033+0.004
Nov 50.029-0.000
Nov 40.029+0.002
Nov 30.027+0.006
Nov 20.021+0.000
Nov 10.020+0.010
Oct 310.010-0.000
Oct 300.010+0.000
Oct 290.010+0.000
Oct 280.010—
82 more days on file for this meter, back to August 7, 2026. Full meter-level history is part of Institutional (API and downloads).
Columbia Gas Transmission (TCO)CGV 01-34

Columbia Gas Transmission (TCO)Placed at the center of Augusta, VA — approximate; the exact meter site is not published.

Recent notices on Columbia Gas Transmission (TCO)

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Columbia Gas Transmission (TCO) notices →

Columbia Gas Transmission (TCO) · posted 2026-11-05 · force majeure
DTM Stonewall Gas Gathering has revised its Force Majeure at the TCO West Braxton delivery meter (842867) upward from 0.550 Bcf/d to 0.900 Bcf/d effective the Evening cycle of 11/05/2026, still with no restoration timeline to full normal capacity. The original FM was declared 9/2…
Columbia Gas Transmission (TCO) · posted 2026-10-27 · effective 2026-11-03 · informational

Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.

Cite thisEnercast PipeScrape, CGV 01-34 (Columbia Gas Transmission (TCO) loc 30CS-34) scheduled quantity, gas day November 26, 2026. https://enercast.com/meter/tco/30cs-34/