EUREKA MIDSTREAM/REX CAMERON MONROE

Rockies Express · Loc 60059 · Ohio
Gathering receipt · counted in Supply / Production
Gas day Nov 27
0.454
Bcf/d scheduled
Δ Day-over-day
+0.000
vs Nov 26
7-day average
0.468
Bcf/d
30-day average
0.418
30 of 30 days posted
30-day high
0.504
Nov 20
30-day low
0.196
Oct 29
Operating capacity
1.000
Bcf/d as posted, evening cycle
Utilization
45%
headroom 55%

Scheduled quantities as posted by Rockies Express on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the Supply / Production page.

0.000.200.400.60Oct 29Nov 3Nov 8Nov 13Nov 18Nov 23 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 270.454+0.000
Nov 260.454-0.008
Nov 250.463+0.015
Nov 240.448-0.039
Nov 230.487-0.004
Nov 220.490+0.010
Nov 210.481-0.023
Nov 200.504+0.036
Nov 190.468+0.000
Nov 180.468-0.014
Nov 170.482-0.008
Nov 160.491-0.001
Nov 150.492+0.001
Nov 140.491+0.036
Nov 130.454+0.120
Nov 120.335-0.044
Nov 110.379+0.033
Nov 100.345-0.093
Nov 90.439+0.010
Nov 80.428+0.002
Nov 70.426-0.026
Nov 60.452+0.047
Nov 50.406-0.045
Nov 40.450+0.067
Nov 30.384-0.007
Nov 20.391+0.025
Nov 10.366+0.162
Oct 310.205+0.000
Oct 300.205+0.009
Oct 290.196—
83 more days on file for this meter, back to August 7, 2026. Full meter-level history is part of Institutional (API and downloads).
Rockies Express

Rockies ExpressState only (Ohio) — the meter's exact site is not geocoded; the ring marks the state, not the point.

Recent notices on Rockies Express

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Rockies Express notices →

Rockies Express · posted 2026-11-16 · effective 2026-11-16 · informational
Rockies Express · posted 2026-10-30 · effective 2026-10-30 · compressor issue
REX Update #19 continues the Bertrand Compressor Station operational issue on Segment 250, raising the West-to-East capacity cap marginally to 1.133 Bcf/d (from 1.094 Bcf/d in Update #18), effective Timely cycle Gas Day November 1, 2026, until further notice. Primary firm, second…

Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.

Cite thisEnercast PipeScrape, EUREKA MIDSTREAM/REX CAMERON MONROE (Rockies Express loc 60059) scheduled quantity, gas day November 27, 2026. https://enercast.com/meter/rex/60059/