PG&E Manchester St, (PROVIDENCE,RI)

Algonquin Gas Transmission · Loc 00087
Power plant delivery · counted in Power Generation
Gas day Nov 27
0.035
Bcf/d scheduled
Δ Day-over-day
+0.000
vs Nov 26
7-day average
0.035
Bcf/d
30-day average
0.052
30 of 30 days posted
30-day high
0.075
Nov 18
30-day low
0.032
Nov 21
Operating capacity
0.130
Bcf/d as posted, late_0005 cycle
Utilization
27%
headroom 73%

Scheduled quantities as posted by Algonquin Gas Transmission on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the Power Generation page.

0.0000.0200.0400.0600.080Oct 29Nov 3Nov 8Nov 13Nov 18Nov 23 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 270.035+0.000
Nov 260.035+0.000
Nov 250.035-0.005
Nov 240.040+0.005
Nov 230.035+0.000
Nov 220.035+0.003
Nov 210.032-0.039
Nov 200.071+0.021
Nov 190.050-0.025
Nov 180.075+0.006
Nov 170.069+0.009
Nov 160.060+0.010
Nov 150.050+0.000
Nov 140.050+0.000
Nov 130.050-0.010
Nov 120.060+0.005
Nov 110.055-0.004
Nov 100.059+0.000
Nov 90.059+0.004
Nov 80.055+0.000
Nov 70.055-0.018
Nov 60.073+0.010
Nov 50.062+0.010
Nov 40.053+0.015
Nov 30.037-0.018
Nov 20.055-0.002
Nov 10.057-0.003
Oct 310.060+0.000
Oct 300.060+0.015
Oct 290.045—
79 more days on file for this meter, back to August 11, 2026. Full meter-level history is part of Institutional (API and downloads).
Algonquin Gas TransmissionPG&E Manchester St, (PROVIDENCE,RI)

Algonquin Gas TransmissionPlant location from EIA Form 860 (plant 3236).

Recent notices on Algonquin Gas Transmission

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Algonquin Gas Transmission notices →

Algonquin Gas Transmission · posted 2026-11-25 · effective 2026-11-27 · informational
Algonquin Gas Transmission · posted 2026-10-30 · effective 2026-10-16 · compressor issue
Algonquin Gas Transmission experienced an unplanned outage at its Weymouth, MA compressor station on Gas Day October 16, 2026. South-to-North nominations through Weymouth will be reduced to 20,000 Dth/d (0.020 Bcf/d) on October 17, then cut to zero beginning October 18 through th…
Algonquin Gas Transmission · posted 2026-10-30 · effective 2026-10-16 · force majeure
Algonquin Gas Transmission declared a force majeure on October 16, 2026 due to an unplanned outage at its Weymouth compressor station in the Boston/New England delivery region. The compressor station is expected to be returned to service by Gas Day October 23, 2026, a duration of…