GILA RIVER PLANT

Transwestern Pipeline · Loc 78480
Power plant delivery · counted in Power Generation
Gas day Nov 27
0.122
Bcf/d scheduled
Δ Day-over-day
+0.033
vs Nov 26
7-day average
0.139
Bcf/d
30-day average
0.147
30 of 30 days posted
30-day high
0.183
Nov 13
30-day low
0.071
Nov 4
Operating capacity
0.485
Bcf/d as posted, evening cycle
Utilization
25%
headroom 75%

Scheduled quantities as posted by Transwestern Pipeline on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the Power Generation page.

0.000.050.100.150.20Oct 29Nov 3Nov 8Nov 13Nov 18Nov 23 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 270.122+0.033
Nov 260.088-0.055
Nov 250.144-0.019
Nov 240.163-0.001
Nov 230.164+0.012
Nov 220.151+0.013
Nov 210.138-0.009
Nov 200.147+0.048
Nov 190.099-0.076
Nov 180.175+0.037
Nov 170.137-0.041
Nov 160.178+0.016
Nov 150.162-0.001
Nov 140.163-0.020
Nov 130.183+0.007
Nov 120.176+0.016
Nov 110.160-0.018
Nov 100.178+0.017
Nov 90.161+0.012
Nov 80.150-0.028
Nov 70.177+0.016
Nov 60.161+0.029
Nov 50.132+0.061
Nov 40.071-0.036
Nov 30.107-0.017
Nov 20.124+0.012
Nov 10.112-0.041
Oct 310.153-0.010
Oct 300.163+0.007
Oct 290.156—
83 more days on file for this meter, back to August 7, 2026. Full meter-level history is part of Institutional (API and downloads).
Transwestern PipelineGILA RIVER PLANT

Transwestern PipelinePlant location from EIA Form 860 (plant 55306).

Recent notices on Transwestern Pipeline

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Transwestern Pipeline notices →

Transwestern Pipeline · posted 2026-11-19 · effective 2026-11-19 · force majeure
Transwestern Pipeline declared force majeure effective November 19, 2026 at 7:15AM due to a compressor station mechanical failure on the West Texas Lateral. Lateral capacity is reduced from 0.830 Bcf/d to 0.750 Bcf/d, a net cut of 0.080 Bcf/d, through November 21, 2026 at 8:59AM.…
Transwestern Pipeline · posted 2026-11-17 · effective 2026-11-14 · informational
Transwestern Pipeline · posted 2026-11-16 · effective 2026-11-14 · force majeure
Transwestern Pipeline has extended its Force Majeure at the WT-0 Compressor Station (Hagerman, NM) from the originally posted single-day event (Gas Day Nov 15 only) through Gas Day November 17, 2026, now spanning three gas days. The mechanical failure reduces West Texas Lateral c…
Transwestern Pipeline · posted 2026-11-15 · effective 2026-11-14 · force majeure
Transwestern Pipeline declared a force majeure on Gas Day November 15, 2026 due to a mechanical failure at the WT-0 Compressor Station in Hagerman, NM, reducing West Texas Lateral capacity from 830,000 MMBtu/d (0.830 Bcf/d) to approximately 750,000 MMBtu/d (0.750 Bcf/d), a net cu…
Transwestern Pipeline · posted 2026-11-04 · effective 2026-10-27 · force majeure
Transwestern East Mainline force majeure, originally declared Oct 27 due to compressor station mechanical failure, has been extended again through Nov 9, 2026 (Revision 2). Capacity remains reduced from 750,000 MMBtu/d to 630,000 MMBtu/d (0.120 Bcf/d net cut), with restoration no…
Transwestern Pipeline · posted 2026-11-02 · effective 2026-11-03 · force majeure
Transwestern Pipeline declared a force majeure due to a compressor station mechanical failure west of Thoreau, reducing westbound capacity from 1.240 Bcf/d to 1.100 Bcf/d (a net cut of 0.140 Bcf/d) effective Gas Day November 3, 2026. The restriction is expected to remain in effec…
Transwestern Pipeline · posted 2026-11-02 · effective 2026-10-27 · force majeure
Transwestern East Mainline force majeure, originally declared Oct 27, has been extended through November 5, 2026 (was Nov 3). East Mainline capacity remains restricted from 750,000 MMBtu/d to 630,000 MMBtu/d, a net reduction of 0.120 Bcf/d. Restoration to full 0.750 Bcf/d capacit…
Transwestern Pipeline · posted 2026-10-28 · effective 2026-10-24 · informational

Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.

Cite thisEnercast PipeScrape, GILA RIVER PLANT (Transwestern Pipeline loc 78480) scheduled quantity, gas day November 27, 2026. https://enercast.com/meter/tw/78480/