Gas day Nov 27
0.089
Bcf/d scheduled
Δ Day-over-day
-0.010
vs Nov 26
7-day average
0.100
Bcf/d
30-day average
0.096
30 of 30 days posted
30-day high
0.197
Nov 15
30-day low
0.000
Oct 31
Operating capacity
0.864
Bcf/d as posted, evening cycle
Utilization
10%
headroom 90%

Scheduled quantities as posted by Transco on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the Power Generation page.

0.000.050.100.150.20Oct 29Nov 3Nov 8Nov 13Nov 18Nov 23 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 270.089-0.010
Nov 260.099-0.040
Nov 250.139+0.040
Nov 240.099+0.015
Nov 230.084-0.019
Nov 220.103+0.019
Nov 210.084-0.020
Nov 200.104+0.000
Nov 190.104-0.006
Nov 180.110-0.030
Nov 170.140-0.050
Nov 160.190-0.007
Nov 150.197+0.091
Nov 140.106+0.005
Nov 130.102-0.009
Nov 120.111+0.040
Nov 110.070-0.017
Nov 100.087+0.025
Nov 90.062+0.022
Nov 80.040+0.000
Nov 70.040-0.037
Nov 60.077-0.040
Nov 50.117-0.008
Nov 40.125-0.010
Nov 30.134+0.044
Nov 20.091+0.082
Nov 10.009+0.009
Oct 310.000-0.064
Oct 300.064-0.036
Oct 290.100—
82 more days on file for this meter, back to August 8, 2026. Full meter-level history is part of Institutional (API and downloads).
TranscoPARK ROAD / CLEVELAND MP 1296.017

TranscoPlaced at the center of Rowan, NC — approximate; the exact meter site is not published.

Recent notices on Transco

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All Transco notices →

Transco · posted 2026-11-06 · effective 2026-11-10 · informational