Sabine Pass LNG (U.S.): 7 active notices, 3 rated severity 4–5; 0 posted in the last 7 days. 2 outages in effect today: 0.400 Bcf/d offline at Gillis Compressor Station, expected back Nov 21; the other has no stated volume. Capacity Offline →
Free: this page refreshes several times a day (delayed) — email & Telegram alerts on a 1-hour delay, severity 4–5 only.
Pro ($189/mo): Real-time alerts within ~2 minutes of posting, full AI trading note. See plans →
Maintenance0.400 Bcf/d cut (capped at 1.130 Bcf/d)Until Further Notice6 Days
Revision 2 of CTPL's 2026 Planned Outage and Maintenance Summary extends the overall coverage window to January 16, 2027 and adds a new job (2026114): a 15-hour compressor maintenance event at Gillis Compressor Station on November 17, with a stated transport impact of 400,000 Dth/d (0.400 Bcf/d) and available capacity of 1.130 Bcf/d. The previously known highest-impact job (2026115, Station Upgrades at Gillis, 11/12-11/18, 6 days) remains unchanged with zero transport impact Dths and a TETCO CT109413 meter limit of zero. The dominant capacity-impact job is 2026115 by duration, but 2026114 carries the larger explicit transport impact at 0.400 Bcf/d for 15 hours.
New 15-hour Gillis compressor maintenance job (2026114, 11/17) posts 0.400 Bcf/d transport impact alongside the ongoing 6-day Station Upgrade (2026115, 11/12-11/18) zeroing the TETCO CT109413 meter, reducing Sabine Pass LNG feedgas throughput and applying bearish pressure on Henry Hub as LNG export capacity is curtailed; live CT109413 row confirms 0.650 Bcf/d operating capacity currently at zero scheduled flow.
Reroute: None: Creole Trail Pipeline is the dedicated feedgas header for Sabine Pass LNG; there is no alternative pipeline path to substitute for Gillis Compressor Station capacity serving this terminal.
Maintenance0.400 Bcf/d cut (capped at 1.130 Bcf/d)Until Further Notice4 Days
Creole Trail Pipeline (CTPL) 2026 Planned Outage and Maintenance Summary updated November 3, 2026 contains two Q4 jobs at Gillis Compressor Station. Job 2026114 on 11/17 (15 hours, gas days 16-17) carries a 400,000 Dth/d (0.400 Bcf/d) transport impact with available capacity of 1,130,000 Dth/d. Job 2026115 (marked as updated, 11/17-11/21, 4 days, gas days 17-20) is a Station Upgrade with zero transport impact but sets the Tetco (CT109461) meter capacity limit to zero for the duration; the 4-day job is the longer constraint window and is treated as the dominant event for duration purposes, while the 0.400 Bcf/d reduction on 11/17 from Job 2026114 represents the largest single-day capacity impact.
CTPL maintenance at Gillis Compressor Station removes 0.400 Bcf/d of Sabine Pass LNG feedgas transport capacity on 11/17 (Job 2026114), and a concurrent 4-day station upgrade (Job 2026115, 11/17-11/21) zeros out the TETCO Gillis meter, applying bearish pressure on Henry Hub as LNG export feedgas is constrained.
Reroute: None: Creole Trail Pipeline is the dedicated CTPL lateral serving Sabine Pass LNG; no alternative pipeline can substitute feedgas supply to this terminal during the outage window.
This is a bundled CTPL 2026 Planned Outage and Maintenance Summary covering two independent jobs. The most impactful single job is Job 2026114 (Q4): a 15-hour compressor maintenance window at Gillis Compressor Station on 11/17/2026 (3:00 a.m. to 6:00 p.m.), with a transport impact of 400,000 Dths (0.400 Bcf/d) and available capacity reduced to 1,130,000 Dths. Job 2026112 (Q3, 9/29-10/2, 4 days) is a LEAP Meter Station upgrade with zero transport impact and should not be treated as a capacity-affecting event.
Job 2026114 removes 0.400 Bcf/d of Sabine Pass LNG feedgas capacity for ~15 hours on 11/17/2026, reducing available CTPL throughput to 1.130 Bcf/d; LNG feedgas curtailment keeps that volume in the domestic market, bearish Henry Hub for that gas day, with the Gillis-LEAP interconnect (CT109461) currently scheduled at 0.735 Bcf/d against 1.00 Bcf/d operating capacity providing partial buffer.
Reroute: Limited: CTPL is the dedicated feed gas pipeline for Sabine Pass LNG; no alternative pipeline directly replaces CTPL feedgas supply to the terminal, though Cheniere may partially offset the 15-hour window through storage or scheduling adjustments.
This is Revision 2 of CTPL's 2026 Q3 planned outage and maintenance summary for Creole Trail Pipeline serving Sabine Pass LNG. The most impactful single job is Job 2026111: Gillis Compressor Station compressor maintenance running 8/25/2026 3:00 a.m. through 8/28/2026 6:00 p.m. (4 days, Gas Days 24-28), with a stated transport impact of 130,000 Dths/day (0.130 Bcf/d) against an available capacity of 1,400,000 Dths/day. The two updated Job 2026113 entries (LEAP Meter Station filter changeouts on 9/8 and 9/9, 9 hours each) show zero transport impact and a meter capacity limit of 475,000 Dths/day at CT109461. Job 2026112 (LEAP Meter Station upgrades 9/29-10/2, 4 days) also shows zero transport impact.
The dominant job in this posting removes 0.130 Bcf/d of CTPL feedgas transport capacity to Sabine Pass LNG for 4 days beginning 8/25/2026; expect mild bearish pressure at Henry Hub as that volume stays in the domestic market, with the CT200111-CREOLE TRAIL-SPLIQ-D delivery point currently running at 88.4% utilization (1.50 Bcf/d scheduled against 1.70 Bcf/d operating capacity), leaving roughly 0.197 Bcf/d of headroom that partially absorbs the constraint.
Reroute: None: CTPL is the dedicated pipeline serving Sabine Pass LNG, and the constraint reduces feedgas transport capacity directly to the terminal with no bypass route available for the curtailed volumes.
View original notice text
Loading…
About Sabine Pass LNG
The Sabine Pass LNG export terminal. Its feedgas pipelines (including Creole Trail) and their compressor stations are what its notices cover; an outage there cuts LNG feedgas.
Operated by
Cheniere Energy
Runs
Cameron Parish, Louisiana
Trading points
Henry Hub, Gulf Coast LNG
Mapped facilities
Gillis
Line from EIA pipeline data; dots are facilities named in this pipeline’s notices (HIFLD locations). Dashed lines are schematic.