Gas Transmission Northwest (U.S.): 13 active notices, 1 rated severity 4–5; 5 posted in the last 7 days. 1 outage in effect today (no volume stated) at Starbuck Compressor Station Unit D, expected back Nov 27. Capacity Offline →
Free: this page refreshes several times a day (delayed) — email & Telegram alerts on a 1-hour delay, severity 4–5 only.
Pro ($189/mo): Real-time alerts within ~2 minutes of posting, full AI trading note. See plans →
Gas Transmission Northwest
UPDATED: CAPACITY REDUCTION: GTN – Flow Past Kingsgate (Updated: 11/11/26)
Force Majeurecapped at 2.800 Bcf/d, cut unknown29 Days
GTN has extended its Force Majeure at Flow Past Kingsgate (LOC #3500) from the previously stated end date of November 7 through November 27, 2026 -- a 20-day extension -- due to the ongoing equipment failure at Wallula Compressor Station Unit A. Available capacity remains capped at 2,800 MMcf/d (2.800 Bcf/d) throughout the extended window, with Firm Primary, Firm Secondary, and Interruptible curtailments all at risk. No pre-event baseline has been provided, so the net reduction relative to normal throughput remains unquantified.
GTN FM extension adds 20 days of Firm Primary curtailment risk at Kingsgate through 11/27 at the 2.800 Bcf/d cap; bullish for Sumas, Stanfield, and PG&E Malin basis as Western Canada import pipeline capacity stays restricted well into late November.
Reroute: Limited: GTN is the primary corridor for Western Canadian gas into the Pacific Northwest and California via Malin; Northwest Pipeline (NWP) provides partial Pacific Northwest coverage but cannot replace Canadian supply volumes constrained at Kingsgate.