Enercast — at the moment it matters
Home / Daily Summary / Supply / Production / Meter

NEXUS/KENSINGTON MR02

NEXUS Gas Transmission (U.S.) · Loc N2002 · Ohio
Processing plant · counted in Supply / Production
Gas day Nov 26
0.292
Bcf/d scheduled
Δ Day-over-day
+0.015
vs Nov 25
7-day average
0.288
Bcf/d
30-day average
0.296
30 of 30 days posted
30-day high
0.318
Oct 31
30-day low
0.277
Nov 25
Operating capacity
1.018
Bcf/d as posted, late_0005 cycle
Utilization
29%
headroom 71%

Scheduled quantities as posted by NEXUS Gas Transmission (U.S.) on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the Supply / Production page.

0.000.100.200.300.40Oct 28Nov 2Nov 7Nov 12Nov 17Nov 22 Bcf/d
Show the 30-day table
Gas dayBcf/dΔ DoD
Nov 260.292+0.015
Nov 250.277-0.002
Nov 240.279-0.013
Nov 230.292+0.000
Nov 220.292+0.001
Nov 210.292-0.001
Nov 200.292+0.000
Nov 190.292+0.000
Nov 180.292+0.000
Nov 170.292+0.000
Nov 160.292+0.000
Nov 150.292+0.002
Nov 140.290-0.012
Nov 130.302-0.005
Nov 120.307+0.000
Nov 110.307+0.015
Nov 100.292+0.000
Nov 90.292+0.000
Nov 80.292+0.000
Nov 70.292+0.000
Nov 60.292+0.000
Nov 50.292-0.005
Nov 40.297+0.010
Nov 30.287-0.015
Nov 20.302+0.001
Nov 10.302-0.016
Oct 310.318+0.000
Oct 300.318-0.000
Oct 290.318+0.026
Oct 280.292—
78 more days on file for this meter, back to August 11, 2026. Full meter-level history is part of Institutional (API and downloads).
NEXUS Gas Transmission

NEXUS Gas TransmissionState only (Ohio) — the meter's exact site is not geocoded; the ring marks the state, not the point.

Recent notices on NEXUS Gas Transmission (U.S.)

Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All NEXUS Gas Transmission (U.S.) notices →

NEXUS Gas Transmission (U.S.) · posted 2026-11-25 · effective 2026-11-25 · informational
NEXUS Gas Transmission (U.S.) · posted 2026-11-18 · effective 2026-11-18 · force majeure
NEXUS Gas Transmission declared force majeure effective November 14, 2026, due to an unplanned outage at the N1002 - NEXUS/DEO MR05 meter station. Restoration timeline is unknown. No capacity volume figure is provided in the notice, so the magnitude of the flow impact is unquanti…

Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.

Cite thisEnercast PipeScrape, NEXUS/KENSINGTON MR02 (NEXUS Gas Transmission (U.S.) loc N2002) scheduled quantity, gas day November 26, 2026. https://enercast.com/meter/nexus/n2002/