Gas day Nov 26
0.130
Bcf/d scheduled
Δ Day-over-day
+0.010
vs Nov 25
7-day average
0.088
Bcf/d
30-day average
0.098
30 of 30 days posted
30-day high
0.130
Nov 26
30-day low
0.066
Nov 13
Operating capacity
0.190
Bcf/d as posted, evening cycle
Utilization
68%
headroom 32%
Scheduled quantities as posted by EGTS on its bulletin board, not metered flow, converted at 1 Bcf/d = 1,000,000 Dth/d. Same figure as this meter’s row on the Supply / Production page.
Last 30 Gas Days
Show the 30-day table
| Gas day | Bcf/d | Δ DoD |
|---|---|---|
| Nov 26 | 0.130 | +0.010 |
| Nov 25 | 0.120 | +0.047 |
| Nov 24 | 0.073 | +0.001 |
| Nov 23 | 0.071 | +0.000 |
| Nov 22 | 0.071 | -0.003 |
| Nov 21 | 0.074 | +0.002 |
| Nov 20 | 0.073 | -0.004 |
| Nov 19 | 0.077 | -0.011 |
| Nov 18 | 0.089 | +0.005 |
| Nov 17 | 0.084 | +0.001 |
| Nov 16 | 0.083 | +0.000 |
| Nov 15 | 0.083 | -0.000 |
| Nov 14 | 0.083 | +0.017 |
| Nov 13 | 0.066 | -0.013 |
| Nov 12 | 0.079 | -0.006 |
| Nov 11 | 0.085 | -0.025 |
| Nov 10 | 0.110 | -0.004 |
| Nov 9 | 0.114 | +0.000 |
| Nov 8 | 0.114 | +0.000 |
| Nov 7 | 0.114 | -0.004 |
| Nov 6 | 0.117 | +0.000 |
| Nov 5 | 0.117 | +0.000 |
| Nov 4 | 0.117 | +0.002 |
| Nov 3 | 0.115 | +0.001 |
| Nov 2 | 0.114 | +0.000 |
| Nov 1 | 0.114 | -0.001 |
| Oct 31 | 0.115 | +0.000 |
| Oct 30 | 0.115 | +0.000 |
| Oct 29 | 0.115 | +0.000 |
| Oct 28 | 0.115 | — |
82 more days on file for this meter, back to August 7, 2026. Full meter-level history is part of Institutional (API and downloads).
Where It Is
Eastern Gas Transmission (EGTS)State only (Pennsylvania) — the meter's exact site is not geocoded; the ring marks the state, not the point.
Notices
Recent notices on EGTS
Severity 3+ in the last 30 days on the same pipeline; not necessarily at this point. All EGTS notices →
EGTS · posted 2026-11-18 · effective 2026-11-19 · informational
EGTS · posted 2026-11-16 · effective 2026-11-17 · informational
SEV 3/5Receipt Restrictions Update
EGTS · posted 2026-11-13 · effective 2026-11-13 · informational
EGTS · posted 2026-11-09 · effective 2026-11-11 · informational
EGTS · posted 2026-11-08 · effective 2026-11-10 · informational
EGTS · posted 2026-11-06 · effective 2026-11-06 · informational
EGTS · posted 2026-11-06 · effective 2026-11-10 · informational
EGTS · posted 2026-11-05 · effective 2026-11-07 · informational
Notices appear here on the free tier’s delay. Pro gets them in real time by email and Telegram.
Other Supply / Production meters on EGTS
- HOLLICK RUN ROAD 0.382 Bcf/d
- PLUM RUN (TL400) 0.295 Bcf/d
- BELL POINT 2 (TL-474/LN-19) 0.272 Bcf/d
- WHITE STATION (TL400) 0.256 Bcf/d
- WAHLVILLE M&R (TL-400) 0.234 Bcf/d
- HUSTED GLENN RD 0.210 Bcf/d
- DENMARK (TL-591) 0.156 Bcf/d
- LEE HILL ROAD 0.141 Bcf/d
Cite thisEnercast PipeScrape, WALNUT (LN26/TL380) (EGTS loc EB785) scheduled quantity, gas day November 26, 2026. https://enercast.com/meter/egts/eb785/