Line Segment 455 Operational Capacity Reduction -- Force Majeure Update (Supersedes #11240)

SEV 4/5Force Majeure0.205 Bcf/d cut (capped at 0.180 Bcf/d)25 days
Summary
Southern Star has declared a force majeure at the Saginaw Compressor Station (Jasper County, MO) due to a mechanical failure of the Saginaw Turbine, reducing capacity by 180,000 Dth/d (0.180 Bcf/d) at Saginaw CS and 25,000 Dth/d (0.025 Bcf/d) at Empire Energy Center, totaling 0.205 Bcf/d. This update (superseding #11240) pushes the in-service date back to November 2, 2026, extending the outage that began ID2 cycle October 9. Live capacity data for Saginaw CS Area Deliveries (loc_id 444550) shows operating capacity at 0.180 Bcf/d with 0.143 Bcf/d scheduled, corroborating the reduced operating cap stated in the notice.
Trading note
Southern Star force majeure at Saginaw CS removes 0.205 Bcf/d of Midcontinent/Missouri delivery capacity through Nov 2; timeline extension is bearish for update direction but the sustained capacity loss is bullish for Southern Star basis -- watch for tightening in Kansas/Missouri LDC markets with limited reroute via ANR, PEPL, or Southern Star alternatives.
Reroute potential
Moderate: ANR and Panhandle Eastern (PEPL) serve overlapping Midcontinent and Midwest corridors and may absorb some volumes, but Southern Star serves specific Kansas/Missouri local markets that have limited direct bypass options.

Get alerts like this, free

Enercast Pipe Monitor tracks critical notices on 190+ U.S. interstate pipelines and scores each one for severity, capacity impact and basis direction. Free subscribers get Severity 4–5 notices by email or Telegram; Pro subscribers get every notice in real time.

View original notice text (as posted by Southern Star)
TSP Name: Southern Star
Notice ID: 11248
Notice Type: Force Majeure
Status: Supersede
Post Date: 2026-10-19T11:06:45.32
Effective Begin: 2026-10-19T11:06:45.32
Effective End: None
Subject: Line Segment 455 Operational Capacity Reduction -- Force Majeure Update (Supersedes #11240)

Update: Contractors are continuing work on the Saginaw Turbine. The in-service date has been pushed back to November 2nd, 2026.
Southern Star Central Gas Pipeline (“Southern Star”) has experienced a Force Majeure mechanical event with a unit at the Saginaw Compressor Station located in Jasper County, Missouri. While repairs are performed, the following capacity reduction will be in place:
Capacity will be reduced as follows:
180,000 Dth/d Saginaw CS (Location ID 444550)
25,000 Dth/d Empire Energy Center (Location ID 378502)
Capacity reduction effective ID2 Cycle October 9th, 2026
Southern Star will provide the status of this above referenced Force Majeure and will provide any changes or updates to this posting as soon as they become available.
We appreciate your assistance during this event and if you have any questions, please feel free to contact your Customer Service Representative or the Scheduling Desk at the numbers listed below.
Scott Warren Office: 270.852.4559 Cell: 270.302.6433
Buster Ashley Office: 270.852.4546 Cell: 270.314.1436
Easton Russelburg: Office 270.852.4546 Cell: 270.302.0173
Robin Joska Office: 270.852.4565 Cell: 270.302.5007
Aingy Mason Office: 270.852.4547 Cell: 270.231.4723
Cite this Enercast Pipe Monitor, “Line Segment 455 Operational Capacity Reduction -- Force Majeure Update (Supersedes #11240)” (Southern Star), posted 2026-10-19. https://enercast.com/notice/southern-star-ss-11248-r1.html
ID: ss-11248  |  Rev. 1  |  Posted: 2026-10-19 16:10  |  Direction: Bullish — in-service date pushed back to Nov 2 (was implied sooner); timeline extension worsens constraint duration All Southern Star notices  ·  page generated 2026-10-19 16:12 UTC