CTPL 2026 Planned Outage and Maintenance Summary – Updated 11.20.26

SEV 4/5Maintenance0.650 Bcf/d10 days
Summary
CTPL's updated 2026 Planned Outage and Maintenance Summary (posted 2026-11-20) contains one active job with a transport impact: Job 2026115, a Station Upgrade at Gillis Compressor Station running 10 days from 11/30/2026 to 12/10/2026. The meter capacity limit for TETCO (CT109413) is set to 0 Dths during this window, effectively zeroing out the TETCO Gillis receipt path into Creole Trail/Sabine Pass LNG, which carries 0.650 Bcf/d of operating capacity on today's EBB. All other jobs listed carry zero transport impact.
Trading note
Gillis Compressor Station upgrade 11/30-12/10 zeros the TETCO Gillis receipt meter (CT109413, currently running 0.060 Bcf/d scheduled against 0.650 Bcf/d operating capacity), removing up to 0.650 Bcf/d of Sabine Pass LNG feedgas receipt capacity and pressuring Henry Hub bearish as LNG export throughput is at risk during the 10-day window.
Reroute potential
Limited: Sabine Pass LNG receives via multiple interconnects (Acadian, LEAP, Trunkline, Transco, TETCO); the TETCO Gillis path (0.650 Bcf/d operating) can potentially be offset by the other receipt meters, but today's scheduling shows the other interconnects already carrying material volumes -- partial offset is possible but full replacement is uncertain over the full 10-day window.

Get alerts like this, free

Enercast Pipe Monitor tracks critical notices on 190+ U.S. interstate pipelines and scores each one for severity, capacity impact and basis direction. Free subscribers get Severity 4–5 notices by email or Telegram; Pro subscribers get every notice in real time.

View original notice text (as posted by Sabine Pass LNG)
Facility: Sabine Pass LNG
Notice ID: 2032
Notice Type: Planned Service Outage
Status: Revision / Supersedes Prior Notice
Title: CTPL 2026 Planned Outage and Maintenance Summary – Updated 11.20.26
Effective Date/Time: 2026-11-20T08:09:00
End Date/Time: 2027-02-28T00:00:00
Posted: 2026-11-20T08:10:23.437
Note: Effective/End Date above is the posting's overall coverage window, NOT necessarily one continuous outage -- see Notice Text and/or the embedded image below for the actual per-job schedule.

Notice Text:
Below is a summary of the CTPL 2026 Planned Outage and Maintenance Projects.     Items marked with * denotes updates from previous posting.   This notice reflects current information as of November 20, 2026. This summary is subject to change as the year progresses to reflect the updated status of all planned outages and maintenance projects. CTPL will post updates as they become available. If you have any questions, please contact Customer Services at 713-375-5900 or email [email protected] .

[EMBEDDED_IMAGE: notice_images/00002032_1.png]
The image above contains this notice's detailed schedule table (fields commonly include Job No., Begin/End dates, Location, Maintenance type, Transport Impact, Available Capacity, and Meter Capacity Limit). This table is NOT present anywhere in this notice as text -- Cheniere delivers it as a picture to every visitor of the page, not just to automated scrapers. Do not treat the Effective/End Date range above as a single continuous outage window: a 'Planned Outage and Maintenance Summary' notice like this one commonly bundles several independent jobs with different dates, locations, and impacts (including some with zero transport impact) into one posting. Read the table in the image directly for accurate per-job dates and capacity figures rather than inferring them from the date range alone.
This notice supersedes a prior filing. Treat as a revision; check for escalation triggers vs prior notice.
Cite this Enercast Pipe Monitor, “CTPL 2026 Planned Outage and Maintenance Summary – Updated 11.20.26” (Sabine Pass LNG), posted 2026-11-20. https://enercast.com/notice/sabine-pass-lng-00002032-r1.html
ID: 00002032  |  Rev. 1  |  Posted: 2026-11-20 14:13  |  Direction: Bearish — initial posting of Job 2026115: 10-day Gillis Compressor Station upgrade 11/30-12/10/2026, meter TETCO (CT109413) capacity limited to 0 Dths (from 0.650 Bcf/d o All Sabine Pass LNG notices  ·  page generated 2026-11-20 14:14 UTC