Vinton Dome Storage Hub Project is a new natural gas storage facility (salt cavern) by Vinton Dome Storage Hub, LLC in LA. It has an application pending and is not yet approved. Stated working gas added is 44.5 Bcf. In-service timing is stated as 2030 (first two caverns). FERC docket CP26-544. Sources: FERC filings, the Federal Register and trade press. Last verified by Enercast on Nov 19, 2026.
| Status | Applied | |
|---|---|---|
| Working gas | 44.5 Bcf stated five caverns, 63.5 Bcf total | |
| Withdrawal | Not stated | — |
| Injection | Not stated | — |
| In-service timing | 2030 (first two caverns) stated | |
| Operator | Vinton Dome Storage Hub, LLC | |
| Project type | New field | |
| Storage type | Salt cavern | |
| States | LA | |
| EIA storage region | South Central | |
| Jurisdiction | Interstate (FERC-regulated) · FERC; LA C&E UIC 2026-02 | |
| FERC docket | CP26-544 | |
| Last verified | Nov 19, 2026 | all sources fetched |
Facts with no source beside them were compiled by Enercast from the documents listed under Sources when the project was first listed.
Working gas, withdrawal and in-service timing are what the source states. None is measured or forecast by Enercast. How to read this page. Updated weekly.
Milestones
No dated milestones recorded yet. They are added as FERC filings, orders and in-service notices appear.
Change log
No changes since this project was first listed on Nov 17, 2026.
Sources
- FERC, Jun 30, 2026: FERC eLibrary CP26-544 (notice of application 2026-06-30)
- Federal Register: FR 2026-18991
- Trade press: NGI
- Trade press: BIC