Spindletop Expansion Project (Golden Triangle Caverns 8, 10, 11, 12)

Golden Triangle Storage, LLC (Caliche) · 30.75 Bcf working gas stated · Under construction

Spindletop Expansion Project (Golden Triangle Caverns 8, 10, 11, 12) is a storage cavern addition (salt cavern) by Golden Triangle Storage, LLC (Caliche) in TX. It is under construction. Stated working gas added is 30.75 Bcf. Stated withdrawal capability added is 1 Bcf/d. In-service timing is stated as late 2028 into early 2029. FERC docket CP25-167. Sources: FERC filings, the Federal Register and trade press. Last verified by Enercast on Nov 19, 2026.

StatusUnder construction
Working gas30.75 Bcf stated
four caverns certificated 2026-03-19; FID on first phase (two caverns) June 2026; NGI put phase 1 at 17 Bcf
Withdrawal1 Bcf/d stated
Injection1 Bcf/d stated
In-service timinglate 2028 into early 2029 stated
OperatorGolden Triangle Storage, LLC (Caliche)
Project typeCavern addition
Storage typeSalt cavern
StatesTX
EIA storage regionSouth Central
JurisdictionInterstate (FERC-regulated) · FERC
FERC docketCP25-167
Last verifiedNov 19, 2026all sources fetched

Facts with no source beside them were compiled by Enercast from the documents listed under Sources when the project was first listed.

Working gas, withdrawal and in-service timing are what the source states. None is measured or forecast by Enercast. How to read this page. Updated weekly.

Milestones

No dated milestones recorded yet. They are added as FERC filings, orders and in-service notices appear.

Change log

No changes since this project was first listed on Nov 17, 2026.