Jefferson Island Storage Hub Expansion (two caverns)

Jefferson Island Storage & Hub, L.L.C. (ONEOK) · 8 Bcf working gas stated · Approved

Jefferson Island Storage Hub Expansion (two caverns) is a storage cavern addition (salt cavern) by Jefferson Island Storage & Hub, L.L.C. (ONEOK) in LA. It is approved but not yet under construction. Stated working gas added is 8 Bcf. In-service timing is stated as 2H 2028 (phase 1), early 2029 (phase 2). Sources: the state regulator and trade press.

StatusApproved
Working gas8 Bcf stated
working capacity ~2 -> ~10 Bcf (RBN)
WithdrawalNot stated—
InjectionNot stated—
In-service timing2H 2028 (phase 1), early 2029 (phase 2) stated
OperatorJefferson Island Storage & Hub, L.L.C. (ONEOK)
Project typeCavern addition
Storage typeSalt cavern
StatesLA
EIA storage regionSouth Central
JurisdictionIntrastate · LA C&E (Injection & Mining)
State permitIMD 2025-07
Last verifiedNot yetall sources fetched

Facts with no source beside them were compiled by Enercast from the documents listed under Sources when the project was first listed.

Working gas, withdrawal and in-service timing are what the source states. None is measured or forecast by Enercast. How to read this page. Updated weekly.

Milestones

No dated milestones recorded yet. They are added as FERC filings, orders and in-service notices appear.

Change log

No changes since this project was first listed on Nov 17, 2026.

Sources

← All new storage projects