Enercast — at the moment it matters
Enercast  /  New Storage  /  Egan Cavern Expansion Project

Egan Cavern Expansion Project

Egan Hub Storage, LLC (Enbridge) · 16 Bcf working gas stated · Approved

Egan Cavern Expansion Project is a storage cavern addition (salt cavern) by Egan Hub Storage, LLC (Enbridge) in LA. It is approved but not yet under construction. Stated working gas added is 16 Bcf. In-service timing is stated as in stages from 2028 through 2033. FERC docket CP26-45. Sources: FERC filings, the Federal Register and the sponsor's public material. Last verified by Enercast on Nov 19, 2026.

StatusApproved
Working gas16 Bcf stated
two caverns of 8.0 Bcf each
WithdrawalNot stated—
InjectionNot stated—
In-service timingin stages from 2028 through 2033 stated
OperatorEgan Hub Storage, LLC (Enbridge)
Project typeCavern addition
Storage typeSalt cavern
StatesLA
EIA storage regionSouth Central
JurisdictionInterstate (FERC-regulated) · FERC
FERC docketCP26-45
Last verifiedNov 19, 2026all sources fetched

Facts with no source beside them were compiled by Enercast from the documents listed under Sources when the project was first listed.

Working gas, withdrawal and in-service timing are what the source states. None is measured or forecast by Enercast. How to read this page. Updated weekly.

Milestones

No dated milestones recorded yet. They are added as FERC filings, orders and in-service notices appear.

Change log

No changes since this project was first listed on Nov 17, 2026.

Sources

← All new storage projects