CTPL 2026 Planned Outage and Maintenance Summary – Updated 11.13.26

SEV 4/5Maintenance0.400 Bcf/d cut (capped at 1.130 Bcf/d)1 days
Summary
CTPL 2026 Planned Outage and Maintenance Summary updated 11/13/2026 bundles three Q4 jobs at Gillis Compressor Station. The two highest-impact jobs (Job 2026114) are short single-day compressor maintenance windows on 11/17 (Gas Days 16-17, 15 hours) and 11/19 (Gas Days 18-19, 16 hours), each reducing available capacity to 1,130,000 Dths with a transport impact of 400,000 Dths. Job 2026115 (Station Upgrades, TBD dates) carries zero transport impact and an available capacity of 1,530,000 Dths. The most impactful single job lasts approximately 15-16 hours on each of the two affected days.
Trading note
CTPL Gillis Compressor maintenance on 11/17 and 11/19 each impose a 0.400 Bcf/d transport impact to Sabine Pass LNG feedgas, capping available capacity at 1.130 Bcf/d per window; expect mild bearish pressure at Henry Hub on each affected gas day as LNG export capacity is temporarily reduced.
Reroute potential
None: Creole Trail Pipeline is a dedicated Sabine Pass LNG feed gas pipeline; there is no alternative routing for volumes curtailed at Gillis Compressor Station.

Get alerts like this, free

Enercast Pipe Monitor tracks critical notices on 190+ U.S. interstate pipelines and scores each one for severity, capacity impact and basis direction. Free subscribers get Severity 4–5 notices by email or Telegram; Pro subscribers get every notice in real time.

View original notice text (as posted by Sabine Pass LNG)
Facility: Sabine Pass LNG
Notice ID: 2026
Notice Type: Planned Service Outage
Status: Revision / Supersedes Prior Notice
Title: CTPL 2026 Planned Outage and Maintenance Summary – Updated 11.13.26
Effective Date/Time: 2026-11-13T09:03:00
End Date/Time: 2026-12-31T00:00:00
Posted: 2026-11-13T09:04:43.25
Note: Effective/End Date above is the posting's overall coverage window, NOT necessarily one continuous outage -- see Notice Text and/or the embedded image below for the actual per-job schedule.

Notice Text:
Below is a summary of the CTPL 2026 Planned Outage and Maintenance Projects.   Items marked with * denotes updates from previous posting.   This notice reflects current information as of November 13, 2026. This summary is subject to change as the year progresses to reflect the updated status of all planned outages and maintenance projects. CTPL will post updates as they become available. If you have any questions, please contact Customer Services at 713-375-5900 or email [email protected] .

[EMBEDDED_IMAGE: notice_images/00002026_1.png]
The image above contains this notice's detailed schedule table (fields commonly include Job No., Begin/End dates, Location, Maintenance type, Transport Impact, Available Capacity, and Meter Capacity Limit). This table is NOT present anywhere in this notice as text -- Cheniere delivers it as a picture to every visitor of the page, not just to automated scrapers. Do not treat the Effective/End Date range above as a single continuous outage window: a 'Planned Outage and Maintenance Summary' notice like this one commonly bundles several independent jobs with different dates, locations, and impacts (including some with zero transport impact) into one posting. Read the table in the image directly for accurate per-job dates and capacity figures rather than inferring them from the date range alone.
This notice supersedes a prior filing. Treat as a revision; check for escalation triggers vs prior notice.
Cite this Enercast Pipe Monitor, “CTPL 2026 Planned Outage and Maintenance Summary – Updated 11.13.26” (Sabine Pass LNG), posted 2026-11-13. https://enercast.com/notice/sabine-pass-lng-00002026-r1.html
ID: 00002026  |  Rev. 1  |  Posted: 2026-11-13 15:07  |  Direction: Bearish — Revision updates two existing Q4 jobs (2026114 dates confirmed, 2026115 TBD) with no change to transport impact figures from prior posting All Sabine Pass LNG notices  ·  page generated 2026-11-13 15:08 UTC