Enercast — at the moment it matters

[FORCE MAJEURE] FORCE MAJEURE - COMP STA 168

SEV 5/5Force MajeureUntil further notice
Summary
NGPL has declared force majeure at Compressor Station 168 in Bailey County, Texas (Segment 8, Permian Zone) due to a unit outage, effective gas day November 19, 2026, continuing until further notice. The scheduling constraint is imposed at CS 167, limiting northbound throughput from Segment 9 into Segment 8; Primary Firm and Secondary in-path Firm will be scheduled to no less than 86% of contract MDQ, while AOR/ITS and Secondary out-of-path Firm are entirely unavailable. Storage withdrawal firm transport and all gas received south of CS 167 for delivery north of CS 167 are impacted for the duration.
Trading note
NGPL CS 168 force majeure curtails northbound Permian Zone throughput to no less than 86% MDQ through CS 167 with AOR/ITS and out-of-path firm eliminated entirely; no concrete Bcf/d cap is stated in the notice and no matching capacity row exists in the live table, but the 14% MDQ haircut on a high-throughput Permian Zone mainline segment is a significant constraint -- expect bearish pressure at NGPL Midcontinent and Amarillo receipt points as northbound takeaway tightens, with bullish pressure at Chicago citygate and Midwest delivery markets.
Reroute potential
Moderate: ANR, PEPL, and REX Zone 3 serve overlapping Gulf Coast-to-Midwest corridors and could absorb some redirected volumes, but NGPL is one of the highest-throughput Midwest pipelines and large-scale reroute is unlikely to fully offset a mainline Permian Zone FM curtailment.

Get alerts like this, free

Enercast Pipe Monitor tracks critical notices on 190+ U.S. interstate pipelines and scores each one for severity, capacity impact and basis direction. Free subscribers get Severity 4–5 notices by email or Telegram; Pro subscribers get every notice in real time.

View original notice text (as posted by Natural Gas Pipeline (NGPL))
Pipeline: Natural Gas Pipeline (NGPL)
Notice Type: FORCE MAJEURE
Subject: FORCE MAJEURE - COMP STA 168
Posted: 11/17/2026 8:58:42AM
Effective: 11/17/2026 8:58:42AM
End Date: 12/31/2026 9:00:00AM

TSP/TSP Name:  6931794-NATURAL GAS PIPELINE CO. Critical: Y
Notice Type Desc (1):  FORCE MAJEURE Notice Type Desc (2):  FORCE MAJEURE
Notice Eff Date/Time:  11/17/2026 8:58:42AM Notice End Date/Time:  12/31/2026 9:00:00am
Post Date/Time:  11/17/2026 8:58:42 AM Notice ID: 47373
Reqrd Rsp:  1 Rsp Date/Time:  11/17/2026 12:00:00 AM
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  FORCE MAJEURE - COMP STA 168
Notice Text:
FORCE MAJEURE – COMPRESSOR STATION 168
 
Natural has experienced a unit outage at Compressor Station 168 (CS 168) located in Bailey County, Texas (Segment 8 of Natural's Permian Zone).  This is a Force Majeure event.  Natural is required to reduce the maximum operating capacity northbound into Segment 8 from Segment 9, thus limiting Natural's throughput capacity northbound through Compressor Station 167 (CS 167).
The scheduling constraint will be at CS 167; therefore, any gas received south of CS 167 for delivery north of CS 167 will be impacted for the duration of the restriction.  The Pooling Point - Permian Zone (LOC 25077) is located south of the constraint.  Firm transportation associated with storage withdrawals may be impacted.
 
As such, effective for gas day Thursday, November 19, 2026, Timely Cycle, and continuing until further notice, Natural will schedule Primary Firm and Secondary in-path Firm transports to no less than 86% of contract MDQ through CS 167.  AOR/ITS and Secondary out-of-path Firm transports will not be available for the duration of this restriction.
 
The stated scheduling percentage is based upon the current level of firm capacity contracted for during this restriction and is subject to change based upon operational conditions and Shipper utilization.
 
Continue to monitor Natural's interactive website for any updates to the end date during this restriction.  Please contact your Account Director or Scheduling Representative if you have any questions.
Cite this Enercast Pipe Monitor, “[FORCE MAJEURE] FORCE MAJEURE - COMP STA 168” (Natural Gas Pipeline (NGPL)), posted 2026-11-17. https://enercast.com/notice/natural-gas-pipeline-ngpl-ngpl-47373-r1.html
ID: NGPL-47373  |  Rev. 1  |  Posted: 2026-11-17 15:01  |  Direction: Bearish All Natural Gas Pipeline (NGPL) notices  ·  page generated 2026-11-17 15:02 UTC