Creekside Lateral Project is a natural gas pipeline lateral project by Kinder Morgan (intrastate) in TX. It is approved but not yet under construction. Stated capacity is 1.3 Bcf/d. In-service timing is stated as fourth quarter of 2026. Source: the sponsor's public material. Last verified by Enercast on Nov 20, 2026.
| Status | Approved | Company, read Nov 20, 2026 |
|---|---|---|
| Capacity | 1.3 Bcf/d stated Design capacity about 1.3 Bcf/d, of which more than 750 MMcf/d is contracted; expansion potential above 2 Bcf/d (sponsor). Enters service in phases; all phases sanctioned. | Company, read Nov 20, 2026 |
| In-service timing | fourth quarter of 2026 company-stated | Company, read Nov 20, 2026 |
| Operator | Kinder Morgan (intrastate) | Company, read Nov 20, 2026 |
| Project type | Lateral | Company, read Nov 20, 2026 |
| States | TX | Company, read Nov 20, 2026 |
| Length | 11 miles | Company, read Nov 20, 2026 |
| Jurisdiction | Intrastate | Company, read Nov 20, 2026 |
| Demand served | Electric, industrial, data centers (Central Texas) | Company, read Nov 20, 2026 |
| Last verified | Nov 20, 2026 | all sources fetched |
Capacity and in-service timing are what the source states. None is measured or forecast by Enercast. How to read this page. Updated weekly. Pro subscribers get daily updates.
Milestones
No dated milestones recorded yet. They are added as FERC orders, construction authorizations and in-service notices appear.
Change log
No changes since this project was first listed on Nov 20, 2026.
Sources
- Company: Kinder Morgan: Projects (Creekside Lateral Project)“KMI's approximately $235 million intrastate Creekside Lateral project is expected to provide more than 750 million cubic feet per day of contracted natural gas transportation to serve growing demand in Central Texas. The project has capacity to transport approximately 1.3 Bcf/d”