[Gulf Run Transmission] [Maintenance] Panola FMJ

SEV 4/5Force Majeure0.900 Bcf/d1 days
Summary
Gulf Run Transmission has declared a Force Majeure at its Panola Compressor Station in Panola County, Texas (Zone 1), effective September 15, 2026 at 09:00, with anticipated restoration by September 16, 2026 at 09:00 -- approximately one calendar day. During this period, throughput capacity at Panola is limited to 0.900 Bcf/d, with upstream point operators warned of elevated pressures and shippers directed to nominate from contractual MRO to MDO locations to minimize scheduling reductions. Pre-event capacity data (gas day 2026-09-09) shows Gemini Panola GR receipt at 0.437 Bcf/d scheduled against 0.800 Bcf/d operating capacity, so the 0.900 Bcf/d throughput cap itself may not immediately bind at current scheduled levels -- but the Force Majeure designation and unplanned nature of the event warrant elevated caution ahead of the effective date.
Trading note
Gulf Run FM at Panola CS caps throughput at 0.900 Bcf/d on Sept 15; this system is built to serve Golden Pass LNG, so any binding curtailment reduces Haynesville-origin feed gas to the LNG corridor and keeps supply in the domestic market, mildly bearish Henry Hub regionally -- watch Golden Pass nominations on Sept 15 for confirmation of actual feed gas impact.
Reroute potential
Moderate: Gulf South and Kinder Morgan assets serve the Haynesville corridor and could absorb some displaced Haynesville supply, but Gulf Run is the primary purpose-built conduit to Golden Pass LNG and no direct replacement pipeline exists for that specific LNG delivery path.

Get alerts like this, free

Enercast Pipe Monitor tracks critical notices on 190+ U.S. interstate pipelines and scores each one for severity, capacity impact and basis direction. Free subscribers get Severity 4–5 notices by email or Telegram; Pro subscribers get every notice in real time.

View original notice text (as posted by Gulf Run Transmission)
Pipeline: Gulf Run Transmission
Notice ID: 68746
Notice Type: Maintenance
Subject: Panola FMJ
Posted: 2026-09-10 12:24:00.0
Effective: 2026-09-15 09:00:00.0
End Date: 

Notice ID: 68746
Notice Type: MAI
Critical: Y
Reqrd Rsp Desc: No Response Required
Posting Date/Time: 2026-09-10 12:24:00.0
Subject: Panola FMJ
Notice Effective Date/Time: 2026-09-15 09:00:00.0
Notice End Date/Time: 2026-12-16 00:00:00.0
Notice Text: This Action Alert is being issued pursuant to GT&C Sections 7 and 8 of Gulf Run’s Tariff and shall constitute notice of an event of Force Majeure at Gulf Run’s Panola Compressor Station located in Panola County, Texas and in Gulf Run’s Zone 1. This unplanned maintenance will occur on Tuesday, September 15th, 2026, with an anticipated completion date of Wednesday, September 16th, 2026, at 09:00. During this time: · Panola Compressor Station will be limited to a throughput capacity of 900,000 dth/d. · Point Operators located in the impacted area will experience higher pressures. Gulf Run will evaluate nominations, on a case by case basis, based on daily operations to alleviate impacts to the extent possible. During this unplanned maintenance, shippers should nominate from their contractual MRO location to their contractual MDO location to reduce risk of scheduling reductions. As more information becomes available, Gulf Run will notify its shippers by updating this posting. If you have any questions concerning this alert, please contact your Scheduling Representative.
ID: GR-68746  |  Rev. 1  |  Posted: 2026-09-10 17:31  |  Direction: Bearish All Gulf Run Transmission notices  ·  page generated 2026-09-26 06:44 UTC